Project · Infrastructure & real assets

Norton Land Port of Entry Modernization

Modernization of the Norton, Vermont land port of entry for U.S. Customs and Border Protection; GSA reported the design 65% complete and environmental review in progress.

Open original Infraday record ↗

Sector
Public Buildings & Civic Infrastructure
Location
Norton, Vermont — approximate project location
Stage / status
Design
Reported value
Estimated $55 million to $65 million
Infrastructure Sector
Public Buildings & Civic Infrastructure
Project Type
Land port of entry modernization
Project Owner / Agency / Developer
U.S. General Services Administration
Estimated Project Value
Estimated $55 million to $65 million
Funding Source
Infrastructure Investment and Jobs Act program
Project Stage
Design
Expected Procurement Date
Construction award anticipated summer 2027
Construction Start
Construction start anticipated summer 2027
Estimated Completion
Substantial completion anticipated summer 2029
Major Scope / Components
Modernize the 1933 land port of entry to improve traffic flow, security and trade and travel operations for U.S. Customs and Border Protection.
Key Organizations Involved
U.S. General Services Administration; U.S. Customs and Border Protection
Engineering / Design Firm
Architect-engineer team engaged; firm not stated on the cited page
Upcoming RFPs / Procurement Opportunities
GSA identifies the next solicitation opportunity as forthcoming; no open deadline is stated.
Permitting / Regulatory Status
Final Environmental Assessment in progress; GSA anticipated NEPA completion in winter 2026.
Major Milestones
2025-09-18 — Public meeting held on the draft environmental assessment.
2026-09-18 — GSA page reported design at 65% and environmental review continuing.
Summer 2027 — Anticipated construction award and start.
Summer 2029 — Anticipated substantial completion.
Recent Project Updates
Development date: 2026-09-18
What changed: GSA reported the design 65% complete while the final environmental assessment remained in progress.
Why it matters: The project is advancing toward a planned summer 2027 construction award, subject to review completion.

History:
2025-09-18 — Public meeting held on the draft environmental assessment.
Challenges / Risks
Schedule remains dependent on environmental review and future procurement.
Website / Procurement Portal
https://www.gsa.gov/real-estate/ongoing-construction-projects/norton-land-port-of-entry-vermont
Last Updated
2026-10-05

Sources & record history

Published Oct 5, 2026 · Record edited Oct 5, 2026 · Sources last reviewed 2026-10-05

GSA project page ↗ · updated 2026-09-18owner, location, budget, stage, design progress, environmental review and schedule

Project / procurement portal ↗Official portal

My Infraday watchlist →

Documented relationships

Editor-sourced links and explicit references in published Infraday records. A named relationship is not a predictive financing match.

No sourced entity relationships have been entered for this record yet.

Explore the same sector

Shared sector only; these records do not establish a commercial relationship or financing fit.

Entity / developmentSector & locationStatus / valueRecord date
ProjectFort Lauderdale U.S. CourthouseA new federal courthouse in Fort Lauderdale with construction reported approximately 80% complete as of April 1, 2026 and completion…Public Buildings & Civic InfrastructureFort Lauderdale, Florida — approximate project locationConstructionSource review: 2026-10-05
ProjectMilwaukee Public Museum Future MuseumNew natural history museum at Sixth and McKinley streets, providing a purpose-built home for collections and exhibits. The museum's groundbreaking…Public Buildings & Civic InfrastructureMilwaukee, WisconsinConstructionSource review: 2026-10-04
ProjectOklahoma City Continental ColiseumNew publicly owned downtown arena and future home of the Oklahoma City Thunder. The city reported concrete placement for the…Public Buildings & Civic InfrastructureOklahoma City, OklahomaConstructionSource review: 2026-10-04
ProjectRochester Downtown Infrastructure UpgradesDMC-funded utility, street and streetscape improvements surrounding Mayo Clinic's downtown development, scheduled to begin in 2026.Public Buildings & Civic InfrastructureRochester, MinnesotaConstructionSource review: 2026-10-03
ProjectBismarck City County Building Renovation and AdditionA comprehensive renovation of the existing City County Building with a south addition, new public entrance, lobby, civic plaza and…Public Buildings & Civic InfrastructureBismarck, North DakotaProcurementDue 2026-10-23Source review: 2026-10-02

CapitalGraph by Infraday · Infrastructure is the launch vertical. Coverage is limited to indexed public records; unknown facts remain blank. Recently edited records first; up to 1,000 projects, 200 articles and 500 records per other section.

Project Atlas · Infraday Capital · Companies · People · RFPs

You’re offline. Reconnect to load the latest Infraday updates.