Project · Infrastructure & real assets
Bismarck City County Building Renovation and Addition
A comprehensive renovation of the existing City County Building with a south addition, new public entrance, lobby, civic plaza and accessible commission chamber.
Open original Infraday record ↗
- Sector
- Public Buildings & Civic Infrastructure
- Location
- Bismarck, North Dakota
- Stage / status
- Procurement
- Infrastructure Sector
- Public Buildings & Civic Infrastructure
- Project Type
- Civic building renovation and addition
- Project Owner / Agency / Developer
- City of Bismarck
- Project Stage
- Procurement
- Expected Procurement Date
- 2026-09-29
- Construction Start
- Construction is anticipated to begin in the first quarter of 2028.
- Delivery Method
- Construction Manager at Risk
- Major Scope / Components
- Preconstruction services, constructability review, cost estimating, schedule and phasing, logistics, value analysis, bid-package development, a new commission chamber addition, first-floor renovation, entrance, stair and elevator tower, civic plaza, site work, and phased renovation of the basement and upper floors.
- Key Organizations Involved
- City of Bismarck; project architect to be coordinated with the selected CMAR
- Current RFPs / RFQs / Bid Opportunities
- Open CMAR RFP; proposals due October 23, 2026 at 4:00 p.m. CT.
- Major Milestones
- 2026-09-29 — City published the CMAR solicitation.
2026-10-23 — Proposals due at 4:00 p.m. CT.
2027-10 — Target for completion of preconstruction phases.
2028-Q1 — Anticipated construction start. - Recent Project Updates
- 2026-10-02 — Official procurement page reviewed; CMAR selection remains open.
- Challenges / Risks
- The occupied facility is expected to remain operational during much of the work, requiring careful phasing, public access and continuity planning.
- Website / Procurement Portal
- https://www.bismarcknd.gov/bids.aspx?bidID=1371
- Last Updated
- 2026-10-02
Sources & record history
Published Oct 2, 2026 · Record edited Oct 2, 2026 · Sources last reviewed 2026-10-02
City of Bismarck CMAR posting ↗ · 2026-09-29owner, scope, delivery method, schedule, procurement status and deadline
Project / procurement portal ↗Official portal
Documented relationships
Editor-sourced links and explicit references in published Infraday records. A named relationship is not a predictive financing match.
No sourced entity relationships have been entered for this record yet.
Explore the same sector
Shared sector only; these records do not establish a commercial relationship or financing fit.
| Entity / development | Sector & location | Status / value | Record date |
|---|---|---|---|
| ProjectNorton Land Port of Entry ModernizationModernization of the Norton, Vermont land port of entry for U.S. Customs and Border Protection; GSA reported the design 65%… | Public Buildings & Civic InfrastructureNorton, Vermont — approximate project location | DesignEstimated $55 million to $65 million | Source review: 2026-10-05 |
| ProjectFort Lauderdale U.S. CourthouseA new federal courthouse in Fort Lauderdale with construction reported approximately 80% complete as of April 1, 2026 and completion… | Public Buildings & Civic InfrastructureFort Lauderdale, Florida — approximate project location | Construction | Source review: 2026-10-05 |
| ProjectMilwaukee Public Museum Future MuseumNew natural history museum at Sixth and McKinley streets, providing a purpose-built home for collections and exhibits. The museum's groundbreaking… | Public Buildings & Civic InfrastructureMilwaukee, Wisconsin | Construction | Source review: 2026-10-04 |
| ProjectOklahoma City Continental ColiseumNew publicly owned downtown arena and future home of the Oklahoma City Thunder. The city reported concrete placement for the… | Public Buildings & Civic InfrastructureOklahoma City, Oklahoma | Construction | Source review: 2026-10-04 |
| ProjectRochester Downtown Infrastructure UpgradesDMC-funded utility, street and streetscape improvements surrounding Mayo Clinic's downtown development, scheduled to begin in 2026. | Public Buildings & Civic InfrastructureRochester, Minnesota | Construction | Source review: 2026-10-03 |