Savannah River clears a step toward supplying fuel for advanced reactors

A storage tank is back in service, but reactor developers still lack a delivery date for the fuel the South Carolina site expects to recover.

Infraday News Desk · Based on official sourcesPublished
Elevated view of H Canyon and the surrounding industrial buildings at the Savannah River Site.
H Canyon at the Savannah River Site in South Carolina on March 17, 2026. Savannah River Site Photography / U.S. Department of Energy · Photo source

The U.S. Department of Energy said on November 24 that its Savannah River Site in South Carolina is ready to begin preparations for uranium recovery at H Canyon. The facility could eventually supply up to 22.8 metric tons of high-assay low-enriched uranium, or HALEU, for advanced reactors. The figure covers the potential output of a multiyear program. DOE gave no date for a first shipment.

The latest announcement follows a decision DOE made in February to recover useful material from fuel already held at the site as part of its cleanup mission. At that point, the department put potential HALEU output from the existing inventory at up to 19 metric tons. Its November estimate is higher. The new announcement gives neither an annual production rate nor a schedule that reactor developers can use to plan deliveries.

A separate development explains what changed on the ground. Savannah River Nuclear Solutions, the site’s managing and operating contractor, returned a long-idled storage tank to service. The additional storage gives workers room to move material already held inside the facility and frees capacity for the recovery work. H Canyon facility manager Kevin Moeller said the workforce had completed planning, maintenance, testing and readiness work for this first stage.

For reactor developers and fuel buyers, the distinction matters when setting a startup schedule. Bringing an existing facility back into service can add a domestic source of fuel, but the November milestone assigns no quantity to an individual buyer. The next evidence to watch for is confirmation that recovery operations have started, followed by a delivery commitment that identifies how much material will be available and when.

Watch for DOE confirmation of initial recovery operations and a dated fuel delivery commitment.

Review the official next step →

Infraday Intelligence

U.S. Department of Energy

Washington, District of Columbia, United States

Federal site owner and sponsor of the recovery mission

Savannah River Nuclear Solutions

Aiken, South Carolina, United States

Site managing and operating contractor responsible for preparing H Canyon

Related research

Primary sources

Have a correction or information about this story? Contact Infraday.

THE INFRADAY WIRE

Your weekly infrastructure briefing.

The projects, investment, companies and developments moving the infrastructure economy, delivered to your inbox.

Projects. Capital. Policy. Markets.

Free weekly newsletter. Unsubscribe anytime.

You’re offline. Reconnect to load the latest Infraday updates.