Energy & Power · PJM region; Mid-Atlantic
PJM raises Valley Link estimate to $5.1 billion as delivery shifts to 2030–2031
Higher construction, land and equipment costs are reshaping a major transmission expansion while the underlying reliability need remains.

PJM reported November 18 that its Board of Managers approved changes raising the estimated cost of the Valley Link projects to approximately $5.1 billion and moving major facilities’ expected service dates into 2030 and 2031.
The earlier estimate was approximately $3 billion in 2024 dollars; the revised figure is expressed in 2026 dollars. The projects include two 765-kilovolt lines and associated substations intended to move electricity across PJM’s west-to-east corridor. Valley Link’s participants include Transource, Dominion Energy and FirstEnergy.
Major components previously targeted June 1, 2029. Their revised dates range from January 2030 to May 2031. PJM identified labor and outside services, land and rights of way, and equipment costs as principal drivers. More detailed routing and regulatory work also changed schedules.
PJM says the reliability needs behind the projects remain and that further delays would extend regulatory processes and increase costs. It attributes the revised schedules to more detailed routing analysis and further permitting and stakeholder work.
Routing, stakeholder consultation and permitting will determine delivery of each Valley Link facility.
Review the official next step →Infraday+ research
PJM Interconnection
PJM’s revised estimate puts Valley Link at about $5.1 billion, with major facilities expected in service in 2030 and 2031.