DOE offers conditional $2.8 billion loan for Wyoming Intertie
The proposed connection would add 1.8 GW of transfer capacity between the eastern and western grids, with financing and permits still to be completed.

The U.S. Department of Energy announced a conditional loan commitment of up to $2.8 billion on November 17 for Grid United’s Wyoming Intertie, advancing a proposed electricity connection between the Eastern and Western Interconnections.
DOE says the project would add approximately 1.8 gigawatts of transfer capacity between the Southwest Power Pool and Western Electricity Coordinating Council regions. The commitment establishes the department’s intent to lend, but the developer must satisfy technical, legal, environmental and financial conditions before definitive documents are signed and funding becomes available.
Grid United describes the project as an approximately 106-mile transmission line through Carbon, Albany and Platte counties, connecting substations near Medicine Bow and Wheatland. The developer estimates investment at approximately $3 billion and says the line could enter service in the early 2030s.
Grid United must secure land rights and permits, and meet DOE’s loan conditions before financing can close.
Review the official next step →Infraday+ research
U.S. Department of Energy
DOE offered a conditional loan commitment of up to $2.8 billion. Financing depends on Grid United meeting the outstanding conditions.