Energy & Power · Beaver County, Utah
Fervo secures another 105 MW of transmission rights for Utah’s Cape Station
Longroad’s agreement takes the geothermal project’s contracted delivery capacity on the Milford line to 505 MW.

Fervo Energy and Longroad Energy signed a long-term transmission service agreement that gives Fervo another 105 megawatts of firm delivery rights for Cape Station in Beaver County, Utah. Fervo announced the deal November 18.
Cape Station already held 400 MW of rights on Longroad’s Milford Gen Lead. The additional reservation raises the total to 505 MW. For a developer bringing geothermal wells into production in stages, access to the line determines how much electricity it can deliver to the grid as each stage comes online.
The agreement changes how much transmission service Fervo has contracted. It does not establish that the plant is producing 505 MW. Fervo expects the additional service to begin in 2028, subject to final regulatory approvals.
Related coverage · DOE Selects 21 Geothermal Projects for More Than $99 Million in Funding Negotiations
Additional transmission service is expected in 2028, subject to final regulatory approvals.
Review the official next step →Infraday+ research
Cape Station Enhanced Geothermal Development
Fervo’s new transmission rights cover delivery on the Milford Gen Lead for its geothermal site in Beaver County · Project Intelligence
Primary sources
- Fervo Energy transmission service announcement · 2026-11-18