Energy & Power · Southeastern New Mexico

Southwest Power Pool selects Longview for 50-mile New Mexico transmission line

The 115-kV line will link four substations in Lea and Eddy counties, with service targeted for June 2029.

Infraday News Desk · Based on official sourcesPublished
Overhead transmission conductors fitted with vibration dampers
Vibration dampers hang from an overhead transmission line. The photograph shows typical line equipment at a separate site. Rsparks3 / CC0 (responsive crop) · Photo source

Southwest Power Pool selected Longview Infrastructure Southwest as the designated owner for a transmission project in southeastern New Mexico on November 17, Longview announced the following day. An independent expert panel evaluated three competing proposals before the regional grid operator made its selection.

Longview will develop approximately 50 miles of 115-kilovolt line connecting the Phantom, Battle Axe, Ponderosa and Dollarhide substations in Lea and Eddy counties. The decision settles which developer is responsible for delivering the line. Longview, a Stonepeak-backed company, says it will now advance development toward an in-service target of June 2029.

Electricity demand from oil and gas operations helps explain the location. Longview said SPP’s 2025 planning work anticipated roughly 4,000 megawatts of additional firm demand on the local utility system as operators electrify drilling. That figure describes demand across the local system. The new line is one part of the network that will have to serve it.

The physical design has two parts. SPP’s February competitive upgrade report calls for a double-circuit connection between Battle Axe and Phantom, plus a new connection from Battle Axe through Ponderosa to Dollarhide. The planning report gives June 1, 2029, as the date by which the grid would need the upgrade.

SPP issued its request for proposals in February. In their October evaluation, five independent panelists compared what each bidder would charge customers over the life of the investment. They also examined how each team would design the line, manage construction, finance the work and operate it once it entered service.

The preferred bid finished 18.9 points ahead of its closest competitor overall. The widest advantage came in the rate analysis, where it led by 19.6 points. The panel cited the bidder’s cost cap, financing terms and guarantees. Its model projected the lowest cost for customers over 40 years. The public report identifies bids by letter and recommends a second bidder as an alternate.

Equipment choices also distinguished the bids. The preferred team proposed a conductor rated to carry 14% more current than the ones in the other two proposals. For customers that will pay for the line through transmission rates, the evaluation sets out what the higher rating buys and how the owner proposes to control costs. Longview’s next task is to deliver that design in time for the region’s June 2029 need.

Related coverage · North Plains Connector’s final environmental review advances a 3,000 MW grid link

Longview targets June 2029 for entry into service.

Review the official next step →

Infraday+ research

Southwest Power Pool

See who selected the transmission owner, which counties the line serves and the targeted in-service date.

Primary sources

You’re offline. Reconnect to load the latest Infraday updates.