Energy & Power · New York, United States
Propel NY names contractors as 90-mile transmission project advances toward construction
New York approved plans for clearing four sites and drilling at two shores, but crews still need written authorization to start either phase.

New York Transco and the New York Power Authority named Burns & McDonnell to build three Long Island substations and The Crossing Group to drill the shore approaches for a cable under Long Island Sound. The developers announced the selections on November 20, a day after the New York Public Service Commission approved two early construction plans for Propel NY Energy. The 90-mile transmission project will connect parts of Long Island, Queens, the Bronx and Westchester County. Before crews can clear trees or drill at either shore, the developers must receive written permission to start.
Who will build the substations and supply the cable
Burns & McDonnell will be the prime contractor for the new Shore Road, Ruland Road and Barrett substations. Each will sit on utility-owned land beside an existing station. Haugland Group and Hitachi Energy will work as subcontractors. The developers also ordered equipment with long manufacturing lead times from SGB-SMIT Group and Hitachi. Their announcement gave no prices for the substations, drilling or equipment.
The Crossing Group will work with Hallen Integrated Construction Services to drill the passages through which the submarine cable will come ashore. Haugland and Hallen already knew the project. In June, the developers selected both firms, along with BOND Civil & Utility Construction, to evaluate design options and help prepare regulatory filings. The November announcement identifies field assignments for Haugland and Hallen. It identifies no construction package for BOND.
LS Cable & System and Taihan will supply underground cable for the land routes and work with local contractors to install and splice it. LS will also supply and install the submarine cable. On November 23, LS valued its own contract at about 700 billion South Korean won and said it had signed in February. Its U.S. subsidiary’s work includes 345-kilovolt cable and testing before the system enters service. The $3.26 billion figure in NYISO’s project selection fact sheet was a capital cost estimate for the entire project.
What crews can do under the two plans
The commission’s September siting decision set conditions for the route and its connections to nine new or existing substations. Phase 1 covers tree clearing at four sites. Three are in Nassau County, at the new Barrett and Shore Road stations and the Shore Road landfall. The fourth is the new Ruland Road station in Suffolk County. Seasonal wildlife restrictions govern when crews can clear each site. Building the stations themselves falls outside this plan.
Phase 2 covers Shore Road in Glenwood Landing, in the Town of Oyster Bay, and Hudson Park and Beach in New Rochelle. At each shore, crews will use horizontal directional drilling to install four conduits to house the cables. In New Rochelle, the plan anticipates drilling over two winters and restoring the park’s parking lot for public use between seasons. Laying the submarine cable itself requires a later construction plan.
Paragraph 3 of each order requires a notice to proceed from the executive director of the state Office of Renewable Energy Siting and Electric Transmission or a designee. Both orders took effect November 20. Infraday found no such notice for either phase in the public case file through November 23. Water quality approval is also under review. The state rescinded an October certification, and the developers filed a new application. Public comments on that application are due November 24.
Why the 2030 date matters to Long Island
The New York Independent System Operator assumed in its 2026 Reliability Needs Assessment that Propel would enter service in May 2030. In that case, Long Island had enough transmission capacity to meet the operator’s summer reliability standard throughout the study. When NYISO removed Propel from the model, the island fell 30 megawatts short in summer 2030. The shortfall grew to 750 megawatts by summer 2036. The comparison measures how much power the system can reliably deliver at peak demand.
The developers’ timetable has already moved once. In June they expected initial work in 2026. They now anticipate site work in early 2027, heavier construction around midyear and delivery in 2030, with crews working in several places at once. They plan to announce contractors for later phases as they complete procurement. Their next public project briefing is scheduled for December 15 at 6 p.m.
Have a correction or information about this story? Contact Infraday.
Water quality comments are due November 24. Each early phase requires a written notice to proceed.
Review the official next step →Infraday+ research
New York Power Authority
Joint developer of Propel NY Energy with New York Transco
Primary sources
- NYPA and New York Transco, Contractor selections and schedule · 2026-11-20
- LS Cable & System, Contract value, signing and scope (in Korean) · 2026-11-23
- New York PSC, November 19 transmission decisions · 2026-11-19
- New York PSC, Phase 1 clearing order, paragraph 3 · 2026-11-20
- New York PSC, Phase 2 landfall order, paragraph 3 · 2026-11-20
- New York DPS, Propel case 24-T-0446, public filings
- New York PSC, Water quality certification order · 2026-11-20
- New York PSC, Water quality comment deadline · 2026-11-09
- NYISO, 2026 Reliability Needs Assessment, pp. 64–65 · 2026-11-18
- New York Transco and NYPA, June preconstruction appointments · 2026-06-29
- NYISO, Project selection and capital cost estimate