Roads & Bridges · Henrico County, Virginia

Henrico begins turnpike widening and first phase of eastern water transmission line

Coordinated road and water construction starts in Henrico, Virginia, with the full transmission line targeted for service in 2031.

Henrico County infrastructure groundbreaking ceremony.
Groundbreaking for the Richmond-Henrico Turnpike improvements and Eastern Henrico Transmission Line. Photo: Henrico County.

At a glance

Road scope
Two lanes to four, plus pedestrian and drainage improvements
Road estimate
US$29.75 million estimated for the road project; excludes the full transmission line
Water scope
Approximately 13 miles of 42-inch main
First phase
Road improvements and approximately one mile of water main scheduled for completion in 2028
Full water line
Expected in service by 2031
Procurement status
Later pipeline phases remain in design; no open solicitation identified in the reviewed sources

Henrico County, Virginia, broke ground on October 28, 2026, on Richmond-Henrico Turnpike improvements and the first section of the Eastern Henrico Transmission Line. The county’s departments of Public Works and Public Utilities are coordinating construction to reduce disruption to residents.

The road project expands the corridor between East Laburnum Avenue and Hummingbird Road from two lanes to four. Plans include a raised median, a west-side sidewalk, an east-side lighted shared-use path and drainage improvements. The county’s road project page lists an estimated cost of $29.75 million; the estimate applies to the road improvements, not the full water transmission line.

The broader water project calls for approximately 13 miles of 42-inch main. The transmission line is intended to enable the county’s treatment facility to supply central and eastern Henrico when needed, improving resilience to disruptions affecting Richmond’s water system. The January 2025 outage accelerated the county’s response.

Project schedule and procurement

The county expects to complete pipeline design in 2027. The road improvements and initial water-main segment of approximately one mile are scheduled for completion in 2028. Construction of the remaining pipeline sections is anticipated to begin that year, with the full line expected to enter service by 2031.

The initial road and utility works are entering construction, while subsequent pipeline phases remain in design. The cited announcements do not identify an open procurement for the remaining sections.


Sources: Henrico County, October 28, 2026; county road project page; 12 On Your Side, October 28, 2026.

What happens next

Pipeline design is expected to be completed in 2027, followed by completion of the initial construction phase in 2028. Full transmission-line service is targeted for 2031.

Source for this milestone →

Why it matters for the industry

Coordinated road and utility construction is intended to reduce disruption to residents. Subsequent pipeline phases remain in design; the cited announcements do not identify an open solicitation.