infradayTHE BUSINESS OF
INFRASTRUCTURE
← Project Atlas
Transportation & Mobility

US-70 Roosevelt Bridge Replacement

US-70 over Lake Texoma, Bryan and Marshall counties, Oklahoma

ConstructionMore than $408 million total project costLast reviewed: 2026-09-30

Sourced project intelligence. Blank fields are shown as “Not yet verified.” Estimates and schedules can change. Check official procurement notices for current deadlines and terms.

Project overview

Infrastructure Sector
Transportation & Mobility
Project Type
Highway bridge replacement
Location
US-70 over Lake Texoma, Bryan and Marshall counties, Oklahoma
Project Owner / Agency / Developer
Oklahoma Department of Transportation
Project Description
Replacement of the existing 80-year-old US-70 Roosevelt Bridge with a new four-lane crossing and upgraded roadway approaches.
Estimated Project Value
More than $408 million total project cost
Funding Source
Federal and state investment, including a $124 million FHWA Bridge Investment Program Large Bridge Project award

Schedule & delivery

Project Stage
Construction
Expected Procurement Date
Not yet verified
Construction Start
September 2026
Estimated Completion
Fall 2029
Delivery Method
Modified progressive design-build
Major Scope / Components
New four-lane bridge; roadway approach improvements; full shoulders; lighting; pedestrian path.

Project team

Key Organizations Involved
Oklahoma Department of Transportation; Federal Highway Administration; U.S. Army Corps of Engineers; Zachry Construction; Traylor Bros.
Prime Contractor / Construction Manager
Zachry Construction / Traylor Bros. design-build team
Engineering / Design Firm
Not yet verified
Technology / Equipment Providers
Not yet verified
Decision Makers / Project Contacts
Not yet verified

Procurement & opportunities

Current RFPs / RFQs / Bid Opportunities
Not yet verified
Upcoming RFPs / Procurement Opportunities
Not yet verified
Contract Value / Package Size
Not yet verified
Workforce Requirements
Not yet verified
Supplier / Subcontractor Opportunities
Not yet verified
Website / Procurement Portal
Official project / procurement website ↗

Progress & intelligence

Permitting / Regulatory Status
ODOT is coordinating environmental considerations with the U.S. Army Corps of Engineers.
Major Milestones
2026-09-10: Ceremonial groundbreaking.
September 2026: Initial site work underway.
Fall 2029: Anticipated completion.
Recent Project Updates
2026-09-30: Added to Project Atlas after verification of active site work, funding and delivery schedule.
Challenges / Risks
Lake foundation work requires drilling and pier construction in water reaching approximately 65 feet near the bridge.
Last Updated
2026-09-30

Project status: Oklahoma DOT has begun a more than $408 million replacement of the 80-year-old US-70 bridge across Lake Texoma between Bryan and Marshall counties.

Why it matters: The new four-lane bridge, approaches, shoulders, lighting and pedestrian path will improve reliability on a corridor carrying more than 11,000 vehicles per day.

Latest verified development: Initial site work is underway after the September 2026 groundbreaking. ODOT expects the new bridge to be complete in fall 2029 while the existing crossing remains open.

Official source: Oklahoma Department of Transportation announcement. Source reviewed September 30, 2026.

You’re offline. Reconnect to load the latest Infraday updates.