INFRADAY PROJECTS · 0173-0534

Shelton Off-Sys Retaining Wall — Shelton (CTDOT 0173-0534)

Shelton, Connecticut · Transportation

Stage: PlanningProcurement: Planned / Forecast

Material research update: 2026-11-15 · Source research checked: 2026-11-15

Saved projects appear in your existing research workspace. Saving does not change email preferences.

Total project estimateUSD 19,377,000
Construction estimateUSD 18,600,000
Expected advertisement2029-08-08Forecast only; not an open bid
Construction startNot verified
Project owner
Connecticut Department of Transportation (managing agency)
Delivery method
Not verified
Expected completion
Not verified

Overview

Replace, rehabilitate, or eliminate deficient retaining wall structures on SR 454 in Shelton, within Pod 3A, that are not on the Federal-Aid Highway System.

Agency project reference
0173-0534

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Design progress
0% recorded design completion

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Additional scope
Replace, rehabilitate, or eliminate deficient retaining wall structures on SR 454 in Shelton, within Pod 3A, that are not on the Federal-Aid Highway System.

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Project type
Capital infrastructure project
Recorded constraints and uncertainties
No open solicitation or bid deadline is verified for this record. Confirm procurement requirements with the relevant agency before pursuing a contract.

Contacts

Corey J. Burroughs

Project lead engineer · CTDOT project team

Project lead engineer identified in the official project record

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.

Opportunities & Contracts

Planned / Forecast

CTDOT records 2029-08-08 as the forecast advertisement date. No current solicitation document, submission deadline or awarded contract package was verified in this research.

Qualification requirements
CTDOT requires prime contractors bidding directly on its advertised construction projects to be prequalified and approved for the specific bid proposal. CTDOT does not require subcontractors to obtain that prime-bidder prequalification. Confirm the actual solicitation and project delivery authority before applying these general rules.

Verified · Connecticut Department of Transportation ↗ · Checked 2026-11-15

Additional scope-based business-development research is available with authorized Infraday+ access.

Companies Involved

Alfred Benesch Company

Consultant engineer identified in the CTDOT project record

Design relationship disclosed; construction award not established

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Budget & Funding

MeaningAmountBasis
Total project estimateUSD 19,377,000CTDOT inventory, source snapshot 2026-11-04

Projected · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Current construction estimateUSD 18,600,000CTDOT inventory, source snapshot 2026-11-04

Projected · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Recorded preliminary engineering expenditureUSD 292,638CTDOT inventory, source snapshot 2026-11-04

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.

Timeline & Milestones

Documents & Resources

Updates & Intelligence

Verified research changes

Research expanded from the official agency record

Added source-attributed contacts, separate cost meanings and forecast milestones. This research addition does not indicate a newly advertised or awarded contract.

Change source ↗
Earlier recorded updates

2026-11-15: Added from official agency inventory. CTDOT lists the schedule phase as 01 Planning. Source snapshot: 2026-11-04. Project estimates and schedules can change.