Route 72 Improvements — Bristol (CTDOT 0017-0196)

Bristol, Connecticut · Transportation

Stage: Final DesignProcurement: Planned / Forecast

Material research update: 2026-11-15 · Source research checked: 2026-11-15

Saved projects appear in your existing research workspace. Saving does not change email preferences.

Total project estimateUSD 13,482,000
Construction estimateUSD 12,600,000
Expected advertisement2027-08-11Forecast only; not an open bid
Construction startNot verified
Project owner
Connecticut Department of Transportation (managing agency)
Delivery method
Not verified
Expected completion
Not verified

Overview

Operational and safety improvements on Route 72 (Riverside Ave) between Main Street and Memorial Boulevard in Bristol, including full depth reconstruction and installation of streetscape appurtenances such as curbing, sidewalks and lighting.

Agency project reference
0017-0196

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Design progress
72% recorded design completion

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Additional scope
Operational and safety improvements on Route 72 (Riverside Ave) between Main Street and Memorial Boulevard in Bristol, including full depth reconstruction and installation of streetscape appurtenances such as curbing, sidewalks and lighting.

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Project type
Capital infrastructure project
Recorded constraints and uncertainties
No open solicitation or bid deadline is verified for this record. Confirm procurement requirements with the relevant agency before pursuing a contract.

Contacts

Kristen A. Levesque

Project lead engineer · CTDOT project team

Project lead engineer identified in the official project record

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.

Opportunities & Contracts

Planned / Forecast

CTDOT records 2027-08-11 as the forecast advertisement date. No current solicitation document, submission deadline or awarded contract package was verified in this research.

Qualification requirements
CTDOT requires prime contractors bidding directly on its advertised construction projects to be prequalified and approved for the specific bid proposal. CTDOT does not require subcontractors to obtain that prime-bidder prequalification. Confirm the actual solicitation and project delivery authority before applying these general rules.

Verified · Connecticut Department of Transportation ↗ · Checked 2026-11-15

Additional scope-based business-development research is available with authorized Infraday+ access.

Companies Involved

Recorded organizations
Connecticut Department of Transportation (managing agency)
Recorded design firm
Consultant

Specific roles and award relationships remain subject to source verification.

Budget & Funding

MeaningAmountBasis
Total project estimateUSD 13,482,000CTDOT inventory, source snapshot 2026-11-04

Projected · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Current construction estimateUSD 12,600,000CTDOT inventory, source snapshot 2026-11-04

Projected · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Recorded preliminary engineering expenditureUSD 136,692CTDOT inventory, source snapshot 2026-11-04

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Recorded right-of-way expenditureUSD 8,485CTDOT inventory, source snapshot 2026-11-04

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.

Timeline & Milestones

Documents & Resources

Updates & Intelligence

Verified research changes

Research expanded from the official agency record

Added source-attributed contacts, separate cost meanings and forecast milestones. This research addition does not indicate a newly advertised or awarded contract.

Change source ↗
Earlier recorded updates

2026-11-15: Added from official agency inventory. CTDOT lists the schedule phase as 03 Final-Design. Source snapshot: 2026-11-04. Project estimates and schedules can change.