Inland Port Greer Rail and Yard Expansion
Greer, South Carolina
Sourced project intelligence. Blank fields are shown as “Not yet verified.” Estimates and schedules can change. Check official procurement notices for current deadlines and terms.
Project overview
- Infrastructure Sector
- Freight & Logistics
- Project Type
- Intermodal terminal expansion
- Location
- Greer, South Carolina
- Project Owner / Agency / Developer
- South Carolina Ports Authority
- Project Description
- The completed expansion adds container capacity, 9,000 feet of rail, a larger chassis lot and new terminal operations and maintenance buildings. The upgraded terminal is designed for 300,000 annual rail lifts.
- Estimated Project Value
- $55 million
- Funding Source
- Included $13.75 million received by SC Ports from a federal BUILD grant administered by SCDOT.
Schedule & delivery
- Project Stage
- Operating / Completed
- Expected Procurement Date
- Not yet verified
- Construction Start
- Not yet verified
- Estimated Completion
- March 2025
- Delivery Method
- Not yet verified
- Major Scope / Components
- The completed expansion adds container capacity, 9,000 feet of rail, a larger chassis lot and new terminal operations and maintenance buildings. The upgraded terminal is designed for 300,000 annual rail lifts.
Project team
- Key Organizations Involved
- Not yet verified
- Prime Contractor / Construction Manager
- Not yet verified
- Engineering / Design Firm
- Not yet verified
- Technology / Equipment Providers
- Not yet verified
- Decision Makers / Project Contacts
- Not yet verified
Procurement & opportunities
- Current RFPs / RFQs / Bid Opportunities
- Not yet verified
- Upcoming RFPs / Procurement Opportunities
- Not yet verified
- Contract Value / Package Size
- Not yet verified
- Workforce Requirements
- Not yet verified
- Supplier / Subcontractor Opportunities
- Not yet verified
- Website / Procurement Portal
- Official project / procurement website ↗
Progress & intelligence
- Permitting / Regulatory Status
- Not yet verified
- Major Milestones
- SC Ports announced completion on March 26, 2025.
- Recent Project Updates
- Not yet verified
- Challenges / Risks
- Not yet verified
- Last Updated
- 2026-10-09
The completed expansion adds container capacity, 9,000 feet of rail, a larger chassis lot and new terminal operations and maintenance buildings. The upgraded terminal is designed for 300,000 annual rail lifts.
Owner: South Carolina Ports Authority
Location: Greer, South Carolina
Published status: Completed
Investment: $55 million
Funding: Included $13.75 million received by SC Ports from a federal BUILD grant administered by SCDOT.
Completion: March 2025
Milestones: SC Ports announced completion on March 26, 2025.
Sources: Official project information. Reviewed October 9, 2026.