Water & Wastewater · Los Angeles, California, United States
LADWP expects $28 million grant for $1 billion water-recycling project
The federal funding would help pay for construction at the Tillman plant, where Los Angeles aims to start purifying recycled water for groundwater recharge in December 2027.

The Los Angeles Department of Water and Power said November 23 that it expects a $28 million federal grant for the Los Angeles Groundwater Replenishment Project. The money would help pay for construction already underway at the Donald C. Tillman Water Reclamation Plant in the San Fernando Valley.
The U.S. Bureau of Reclamation previously awarded $60 million to the project, according to LADWP. The additional award would bring the bureau’s contribution to $88 million toward what the utility describes as a $1 billion investment. LADWP says federal funding helps limit the cost passed on to water customers. It gave no estimate of the effect on bills.
What the federal money would cover
LADWP and Los Angeles Sanitation and Environment are adding a purification facility to the existing Tillman plant. Construction began in December 2024. Jacobs already holds the progressive design-build contract for the facility, including startup and commissioning. The November announcement identifies construction at Tillman as the use for the money and gives no revised timetable.
Reclamation first selected the Los Angeles project for $30 million in May 2024. The bureau set that money aside for final design and construction at both the existing treatment plant and the new purification facility. That award counts toward the $60 million LADWP reported before the latest announcement. The bureau’s public listing for the 2026 competition still describes applications as under review.
How much water Tillman can treat
Tillman already treats wastewater from homes and businesses for uses including irrigation. The new facility will take water that has passed through the existing treatment process and purify it in three more steps. Membrane filtration removes fine particles, reverse osmosis separates dissolved substances from the water, and ultraviolet light drives an advanced oxidation process that breaks down compounds left after filtration.
Jacobs puts the facility’s treatment capacity at up to 30 million gallons of incoming water a day. The design allows for a later expansion to 45 million gallons a day, the figure LADWP cited in its announcement. Jacobs says it worked with city staff to reduce water lost in the existing plant’s processes, making more water available for purification. The city’s May engineering report illustrates the difference between intake and output. It modeled treating up to 25 million gallons of incoming water a day to produce up to 20 million gallons of purified water a day.
Incoming flows also vary over the course of a day. Two equalization tanks, each designed to hold 4.6 million gallons, give operators room to absorb those swings. The plant needs more electricity to run the additional treatment equipment. Alongside electrical upgrades at Tillman, LADWP plans about two miles of underground conduits and vaults for a new power connection that can serve the site during peak demand.
From the plant to the San Fernando basin
LADWP will pump purified water through an existing pipeline to the Hansen Spreading Grounds. There, Los Angeles County Public Works will tell the utility when the basins have room to receive it. The city’s draft engineering report anticipates that most deliveries will take place in dry weather. During storms, how much purified water the grounds can accept will depend on how much capacity is left after taking in stormwater.
The report describes a change at the receiving end of the pipeline. The city plans to refurbish an existing outlet and add a second one at another basin. That arrangement would let operators keep delivering purified water to one part of the grounds while another is receiving stormwater or is out of service for maintenance.
Water released at Hansen will filter through the soil into the San Fernando Groundwater Basin. LADWP expects it to stay underground for several years. Existing wells will eventually recover the groundwater, which will receive further treatment before it enters the city’s drinking-water system.
The Bureau of Reclamation is the agency that can confirm the additional award. For LADWP, LA Sanitation and Jacobs, the next operating milestone is startup. LADWP targets December 2027 for the project to go online. Jacobs also puts startup in 2027 and lists final completion of its work in 2028.
Have a correction or information about this story? Contact Infraday.
Why it matters
The anticipated grant would increase federal support for construction already underway from $60 million to $88 million.
LADWP targets December 2027 for operations at Tillman.
Review the official next step →Infraday Intelligence
Jacobs
Dallas, TX (global headquarters)Jacobs
Bureau of Reclamation
United StatesBureau of Reclamation
Los Angeles Department of Water and Power
Los Angeles, CALos Angeles Department of Water and Power
Primary sources
- Los Angeles Department of Water and Power, November funding announcement · 2026-11-23
- Bureau of Reclamation, Large-Scale Water Recycling Program
- Bureau of Reclamation, May 2024 project selections
- LADWP and LA Sanitation and Environment, draft engineering report, sections 4 and 7 · 2026-05-01
- LADWP, groundwater replenishment project and operating timeline
- Jacobs, Donald C. Tillman Advanced Water Purification Facility
- LADWP, Victory Electrical Conduit Project
- LADWP, groundwater replenishment executive overview, slides 9 and 12 · 2026-06-05
- LADWP, May 2024 federal water funding award · 2024-05-29