Water & Wastewater · Los Angeles, California, United States

LADWP expects $28 million grant for $1 billion water-recycling project

The federal funding would help pay for construction at the Tillman plant, where Los Angeles aims to start purifying recycled water for groundwater recharge in December 2027.

Infraday News Desk · Based on official sourcesPublished
Crews work among concrete walls, reinforcing steel and timber forms at the Tillman Water Reclamation Plant in Los Angeles.
Construction at the Donald C. Tillman Water Reclamation Plant in Van Nuys during an April 16, 2026, site visit. City of Los Angeles, Office of Mayor Karen Bass, press handout. · Photo source

The Los Angeles Department of Water and Power said November 23 that it expects a $28 million federal grant for the Los Angeles Groundwater Replenishment Project. The money would help pay for construction already underway at the Donald C. Tillman Water Reclamation Plant in the San Fernando Valley.

The U.S. Bureau of Reclamation previously awarded $60 million to the project, according to LADWP. The additional award would bring the bureau’s contribution to $88 million toward what the utility describes as a $1 billion investment. LADWP says federal funding helps limit the cost passed on to water customers. It gave no estimate of the effect on bills.

What the federal money would cover

LADWP and Los Angeles Sanitation and Environment are adding a purification facility to the existing Tillman plant. Construction began in December 2024. Jacobs already holds the progressive design-build contract for the facility, including startup and commissioning. The November announcement identifies construction at Tillman as the use for the money and gives no revised timetable.

Reclamation first selected the Los Angeles project for $30 million in May 2024. The bureau set that money aside for final design and construction at both the existing treatment plant and the new purification facility. That award counts toward the $60 million LADWP reported before the latest announcement. The bureau’s public listing for the 2026 competition still describes applications as under review.

How much water Tillman can treat

Tillman already treats wastewater from homes and businesses for uses including irrigation. The new facility will take water that has passed through the existing treatment process and purify it in three more steps. Membrane filtration removes fine particles, reverse osmosis separates dissolved substances from the water, and ultraviolet light drives an advanced oxidation process that breaks down compounds left after filtration.

Jacobs puts the facility’s treatment capacity at up to 30 million gallons of incoming water a day. The design allows for a later expansion to 45 million gallons a day, the figure LADWP cited in its announcement. Jacobs says it worked with city staff to reduce water lost in the existing plant’s processes, making more water available for purification. The city’s May engineering report illustrates the difference between intake and output. It modeled treating up to 25 million gallons of incoming water a day to produce up to 20 million gallons of purified water a day.

Incoming flows also vary over the course of a day. Two equalization tanks, each designed to hold 4.6 million gallons, give operators room to absorb those swings. The plant needs more electricity to run the additional treatment equipment. Alongside electrical upgrades at Tillman, LADWP plans about two miles of underground conduits and vaults for a new power connection that can serve the site during peak demand.

From the plant to the San Fernando basin

LADWP will pump purified water through an existing pipeline to the Hansen Spreading Grounds. There, Los Angeles County Public Works will tell the utility when the basins have room to receive it. The city’s draft engineering report anticipates that most deliveries will take place in dry weather. During storms, how much purified water the grounds can accept will depend on how much capacity is left after taking in stormwater.

The report describes a change at the receiving end of the pipeline. The city plans to refurbish an existing outlet and add a second one at another basin. That arrangement would let operators keep delivering purified water to one part of the grounds while another is receiving stormwater or is out of service for maintenance.

Water released at Hansen will filter through the soil into the San Fernando Groundwater Basin. LADWP expects it to stay underground for several years. Existing wells will eventually recover the groundwater, which will receive further treatment before it enters the city’s drinking-water system.

The Bureau of Reclamation is the agency that can confirm the additional award. For LADWP, LA Sanitation and Jacobs, the next operating milestone is startup. LADWP targets December 2027 for the project to go online. Jacobs also puts startup in 2027 and lists final completion of its work in 2028.

Have a correction or information about this story? Contact Infraday.

Why it matters

The anticipated grant would increase federal support for construction already underway from $60 million to $88 million.

LADWP targets December 2027 for operations at Tillman.

Review the official next step →

Infraday Intelligence

Jacobs

Dallas, TX (global headquarters)

Jacobs

Bureau of Reclamation

United States

Bureau of Reclamation

Los Angeles Department of Water and Power

Los Angeles, CA

Los Angeles Department of Water and Power

Primary sources

You’re offline. Reconnect to load the latest Infraday updates.