Water & Wastewater · San Francisco, California

San Francisco’s storm overwhelmed its sewers. The Mission’s relief tunnel is still in design

The city finished upgrading smaller pipes near 17th and Folsom last year. A planned 4,000-foot tunnel would give stormwater another route out of the low-lying neighborhood.

Infraday News Desk · Based on official sourcesPublished
A satellite view shows the spiral of clouds offshore and a band of clouds reaching California.
The storm off California on November 18, 2026, as seen by satellite. NASA EOSDIS Worldview, public domain · Photo source

At La Scuola International School in San Francisco’s Mission District, staff saw water rise out of a manhole during the November 18 storm. The San Francisco Public Utilities Commission told ABC7 that rain fell faster than the sewer system could carry it away. ABC7 reported that the city’s 311 service logged more than 1,000 flooding and sewer-related reports that day.

The low ground around 17th, 18th and Folsom streets was a known trouble spot well before this storm. Even moderate rain can cause flooding there, according to the utility. In 2025, crews finished upgrading about 2,855 feet of smaller sewer pipe in the first phase of the Folsom Area Stormwater Improvement Project.

Where the water would go

The next phase includes a tunnel 12 feet in diameter running roughly 4,000 feet from Alameda and Florida streets toward 7th and Berry streets. The additional route would let the system carry more water away from the neighborhood during a downpour. SFPUC says it is finishing the design and discussing contracting options with builders in a competitive tunneling market. Its project page lists further phases in 2027 and completion in 2030.

That timetable leaves property owners facing several more rainy seasons before the work is complete. The utility also expects some flood risk to persist afterward. On November 20, it reminded owners that its Floodwater Grant program offers eligible properties up to $100,000 for protective work. A backwater valve, for example, can keep sewage from flowing backward through plumbing fixtures. Owners start with an interest form and a site visit.

SFPUC lists further phases in 2027 and overall completion in 2030. It says it will update the contracting timeline.

Review the official next step →

Infraday+ research

San Francisco Public Utilities Commission

The utility completed the first phase of the Folsom project in 2025 and is finalizing the design for its 12-foot-diameter tunnel.