Rail & Transit · Chicago, Illinois

Amtrak advances $112 million level-boarding project at Chicago Union Station

Former mail platforms will become passenger facilities and provide capacity during later station reconstruction.

Infraday News Desk · Based on official sourcesPublished
A Metra train alongside a platform at Chicago Union Station.
A Metra train at Chicago Union Station in September 2026. Amtrak’s level-boarding project covers the former mail platforms on tracks 30 through 38. Phil Richards / CC BY-SA 4.0 · Photo source

Amtrak announced November 9 that it is moving a $112 million platform project at Chicago Union Station into construction, with major work expected before year-end. The 30-month effort will convert former mail and parcel platforms into accessible passenger facilities.

The work covers platforms serving tracks 30 through 38 and includes a climate-controlled waiting area and restrooms. Level boarding will allow passengers to reach trains without stairs, ramps or lifts. The facilities will also provide interim capacity while other platforms are rebuilt.

Clark Construction is the general contractor, WSP USA remains designer of record and HNTB will provide project and construction management. Funding combines a $49.6 million federal partnership grant, $40 million in federal appropriations and $22.4 million in local contributions.

This is the first Chicago Hub Improvement Program project to reach construction. Amtrak’s wider program also includes station modernization, platform ventilation work and bridge improvements at different stages. The immediate milestone is mobilizing the platform work while preserving service through one of the Midwest’s central rail hubs.

Amtrak expects major construction before the end of 2026, with platform conversion taking about 30 months.

Review the official next step →

Infraday+ research

Amtrak

Amtrak’s $112 million Chicago program will convert former mail platforms for level boarding on tracks 30 through 38.

Primary sources

You’re offline. Reconnect to load the latest Infraday updates.