Capital & Policy · Olyphant, Pennsylvania

Olyphant approves $101 million community benefits agreement for seven proposed data centers

Two 5–2 votes settled a land-use dispute and approved a 15-year benefits agreement. Project Triboro still faces local review of its development plans.

Infraday News Desk · Based on official sourcesPublished
Paris Digital Park data center exterior in La Courneuve, France
Paris Digital Park in La Courneuve, France, photographed October 8, 2026. Illustrative data center photograph. Guallendra / Wikimedia Commons, CC0 · Photo source

Olyphant Borough Council voted 5–2 on November 17 to settle a lawsuit brought by ERCOR Triboro LLC over a proposed data center campus in Lackawanna County, Pennsylvania. In a second vote by the same margin, council approved a 15-year, $101 million community benefits agreement, The Times-Tribune reported from the meeting.

ERCOR wants to build seven data centers of 420,000 square feet each and a substation on land previously approved for four warehouses near Marshwood Road and Route 247. The settlement lets the developer proceed without a conditional-use hearing, where residents could have questioned the developer’s representatives and introduced evidence.

The revised site plans still go through the borough planning commission. That distinction mattered to residents at the special meeting. The Times-Tribune reported that all 27 members of the public who spoke urged council to delay or reject the deal.

Electric service presents a separate question. At an October council meeting, borough officials said Olyphant would need a formal request for power before it could proceed with a line to the site. The $101 million is the value of the community agreement over its 15-year term.

Status and next steps

The developer must bring its revised land-development plans before Olyphant’s planning commission.

Review the official next step →

Project contacts and next steps

A direct project contact has not been verified for this article. Consult the linked source organization for the appropriate office.

Primary sources

You’re offline. Reconnect to load the latest Infraday updates.