Capital & Policy · United States
Senate permitting bill would make large data centers pay for grid upgrades and existing lines
A bipartisan proposal pairs faster energy-project reviews with a change in how utilities recover transmission costs from large data center customers.

A bipartisan permitting bill would change the price of a grid connection for large U.S. data centers. Under the Bipartisan American Affordability and Jobs Act, utilities would have to recover both a data center’s share of the existing transmission network and the cost of upgrades needed to serve its demand.
What utilities would charge
The Senate Energy and Natural Resources Committee says the bill would direct the Federal Energy Regulatory Commission to change the rules utilities use to set those rates. For a developer comparing sites, that puts two costs on the table. A new line or substation could carry its own charge on top of the cost of using the network already in place.
States could use the additional revenue to reduce rates for households and other customers. The proposal also calls for utilities to report electricity sales to data centers, giving regulators a clearer view of how much power those facilities buy.
The trade-off extends beyond electricity bills. As Brad Plumer reported for The New York Times, the wider package would accelerate federal reviews for infrastructure such as high-voltage lines and gas pipelines. Faster approvals could help bring power to a site sooner, even as the proposed rate rules would give the operator a larger share of the bill.
Status and next steps
The proposed rate changes depend on enactment and subsequent federal regulatory action.
Review the official next step →Project contacts and next steps
A direct project contact has not been verified for this article. Consult the linked source organization for the appropriate office.