Roads & Bridges · Madison, Wisconsin

Madison’s Pflaum Road Reconstruction Moves From Utilities to Pavement

Madison reports that first-phase sanitary sewer, water-main and storm-sewer work is complete on its Pflaum Road reconstruction. The October 16 update says crews are preparing the new roadway between Kvamme Lane and South Stoughton Road before concrete pavement, curbs, driveways and sidewalks are installed.

At a glance

Status
Construction
Contract
8747
Estimated schedule
August 3, 2026 to August 27, 2027
First-phase utilities
Complete as of October 16 update

Madison reports that first-phase sanitary sewer, water-main and storm-sewer work is complete on its Pflaum Road reconstruction. The October 16 update says crews are preparing the new roadway between Kvamme Lane and South Stoughton Road before concrete pavement, curbs, driveways and sidewalks are installed.

Grading and concrete work at the Stoughton Road intersection require a temporary restriction on its service road. Northbound access remains available while the southbound lane is closed; the city expected the restriction to last at least two weeks.

The wider program reconstructs Pflaum Road from Stoughton Road to Monona Drive and adds a separated shared-use path. Its published schedule divides delivery between 2026 and 2027.

The first section is scheduled to finish in November 2026, with the remaining section planned for spring through August 2027. These are city forecasts. The reviewed project page does not establish a total investment value.

Official project page and October 16 update. Source rechecked November 1, 2026. · Pflaum Road project record.

What happens next

After gravel placement, the city identifies concrete pavement, curb, driveways and sidewalk as the next major milestone. The 2026 section is scheduled for completion in November, with the wider project scheduled through August 27, 2027.

Source for this milestone →

Why it matters for the industry

The work packages roadway, water, sanitary sewer, storm sewer and a separated shared-use path. The current official page does not state a total project investment value.

Supporting source →