US 101 Ocean Beach Road to Jefferson County Line Paving
Jefferson County, Grays Harbor County, Washington · Transportation, Highways and bridges
Source research checked: 2026-11-06
Saved projects appear in your existing research workspace. Saving does not change email preferences.
- Project owner
- Washington State Department of Transportation
- Delivery method
- Not verified
- Expected completion
- Not verified
Overview
Preserve approximately 50 miles of US 101 through resurfacing, including an added section toward Kalaloch scheduled for work in 2027.
Technical scope
Preserve approximately 50 miles of US 101 through resurfacing, including an added section toward Kalaloch scheduled for work in 2027.
Agency-published project contact: Bonnie Kramer | Project Engineer | 360-538-8502 | Bonnie.Kramer@wsdot.wa.gov
Contact source: https://wsdot.wa.gov/construction-planning/search-projects/us-101-ocean-beach-road-jefferson-county-line-paving
- Project type
- Road, bridge and multimodal improvements
Contacts
Recorded professional contact
Bonnie Kramer | Project Engineer | 360-538-8502 | Bonnie.Kramer@wsdot.wa.gov
Recorded contact information. Current role and contact reachability have not been independently rechecked; confirm through the linked source before outreach.
Recorded contact source ↗Source check recorded: 2026-11-06
Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.
Opportunities & Contracts
No procurement verified
No linked, currently verified solicitation has been established for this project.
Companies Involved
- Recorded contractor
- Lakeside Industries, Inc (agency-reported award: April 2026)
Specific roles and award relationships remain subject to source verification.
Budget & Funding
- Recorded funding
- $31.4 million covers design and construction for three paving sections; the added Kalaloch section is not assumed to be included.
Agency funding detail (2026-11-06): Budget: $31.4 million for design and construction of the original three paving sections. This excludes the fourth section added in September 2026; the revised four-section total is pending.
Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.
Timeline & Milestones
- Recorded construction start
- Spring 2027: Expected start of construction between Jefferson County line and Kalaloch
- Recorded milestones
- Agency-listed project timeline: Spring 2026 – Fall 2027. Agency stage: Construction.
Agency milestone schedule (reviewed 2026-11-06):
April 2026: Contract awarded to Lakeside Industries, Inc.
June 22, 2026: Start of paving work between Queets and Lake Quinault
Aug. 13, 2026: Paving between Queets and Lake Quinault completed
Aug. 14, 2026: Paving work starts between Humptulips and Neilton
Sept. 17, 2026: Paving between Humptulips and Neilton completed
Sept. 18, 2026: Start of paving between New London and Axford
Sept. 29, 2026: Fourth section of paving added to project from Jefferson County line to Kalaloch
Fall 2026: Expected completion of construction, sections 1-2
Spring 2027: Expected start of construction between Jefferson County line and Kalaloch
Fall 2027: Construction expected to be complete between Jefferson County line and Kalaloch
Documents & Resources
- WSDOT official project page ↗Reviewed 2026-11-06
Updates & Intelligence
Earlier recorded updates
2026-11-06: Newly indexed from the agency project page. Agency-listed project timeline: Spring 2026 – Fall 2027. Agency stage: Construction. Procurement availability has not been verified.
2026-11-06: Official-source enrichment added or expanded contacts, milestones, funding, start, contractor, scope. Planned procurement milestones do not establish an open bid.
Detailed research and a source-backed change history are being assembled. A routine source check is not a material project update.