US 101 Ocean Beach Road to Jefferson County Line Paving

Jefferson County, Grays Harbor County, Washington · Transportation, Highways and bridges

Stage: ConstructionProcurement: No procurement verified

Source research checked: 2026-11-06

Saved projects appear in your existing research workspace. Saving does not change email preferences.

Recorded project valueNot verified
Construction estimateNot separately verified
Recorded procurement milestoneNot verifiedSee the source and current procurement status.
Construction startSpring 2027: Expected start of construction between Jefferson County line and Kalaloch
Project owner
Washington State Department of Transportation
Delivery method
Not verified
Expected completion
Not verified

Overview

Preserve approximately 50 miles of US 101 through resurfacing, including an added section toward Kalaloch scheduled for work in 2027.

Technical scope

Preserve approximately 50 miles of US 101 through resurfacing, including an added section toward Kalaloch scheduled for work in 2027.

Agency-published project contact: Bonnie Kramer | Project Engineer | 360-538-8502 | Bonnie.Kramer@wsdot.wa.gov
Contact source: https://wsdot.wa.gov/construction-planning/search-projects/us-101-ocean-beach-road-jefferson-county-line-paving

Project type
Road, bridge and multimodal improvements

Contacts

Recorded professional contact

Bonnie Kramer | Project Engineer | 360-538-8502 | Bonnie.Kramer@wsdot.wa.gov

Recorded contact information. Current role and contact reachability have not been independently rechecked; confirm through the linked source before outreach.

Recorded contact source ↗

Source check recorded: 2026-11-06

Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.

Opportunities & Contracts

No procurement verified

No linked, currently verified solicitation has been established for this project.

Companies Involved

Recorded contractor
Lakeside Industries, Inc (agency-reported award: April 2026)

Specific roles and award relationships remain subject to source verification.

Budget & Funding

Recorded funding
$31.4 million covers design and construction for three paving sections; the added Kalaloch section is not assumed to be included.
Agency funding detail (2026-11-06): Budget: $31.4 million for design and construction of the original three paving sections. This excludes the fourth section added in September 2026; the revised four-section total is pending.

Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.

Timeline & Milestones

Recorded construction start
Spring 2027: Expected start of construction between Jefferson County line and Kalaloch
Recorded milestones
Agency-listed project timeline: Spring 2026 – Fall 2027. Agency stage: Construction.
Agency milestone schedule (reviewed 2026-11-06):
April 2026: Contract awarded to Lakeside Industries, Inc.
June 22, 2026: Start of paving work between Queets and Lake Quinault
Aug. 13, 2026: Paving between Queets and Lake Quinault completed
Aug. 14, 2026: Paving work starts between Humptulips and Neilton
Sept. 17, 2026: Paving between Humptulips and Neilton completed
Sept. 18, 2026: Start of paving between New London and Axford
Sept. 29, 2026: Fourth section of paving added to project from Jefferson County line to Kalaloch
Fall 2026: Expected completion of construction, sections 1-2
Spring 2027: Expected start of construction between Jefferson County line and Kalaloch
Fall 2027: Construction expected to be complete between Jefferson County line and Kalaloch

Documents & Resources

Updates & Intelligence

Earlier recorded updates

2026-11-06: Newly indexed from the agency project page. Agency-listed project timeline: Spring 2026 – Fall 2027. Agency stage: Construction. Procurement availability has not been verified.
2026-11-06: Official-source enrichment added or expanded contacts, milestones, funding, start, contractor, scope. Planned procurement milestones do not establish an open bid.

Detailed research and a source-backed change history are being assembled. A routine source check is not a material project update.