US 101/ Fort Columbia Tunnel – Concrete Panel Replacement/Rehab
Pacific County, Washington · Transportation, Highways and bridges
Source research checked: 2026-11-06
Saved projects appear in your existing research workspace. Saving does not change email preferences.
- Project owner
- Washington State Department of Transportation
- Delivery method
- Not verified
- Expected completion
- Late 2027: Construction scheduled for completion
Overview
Replace damaged concrete roadway panels in the US 101 Fort Columbia Tunnel to improve the surface and extend pavement life.
Technical scope
Replace damaged concrete roadway panels in the US 101 Fort Columbia Tunnel to improve the surface and extend pavement life.
Agency-published project contact: Kelso Area Engineering Office | (360) 905-1599 | swkelso@wsdot.wa.gov
Contact source: https://wsdot.wa.gov/construction-planning/search-projects/us-101-fort-columbia-tunnel-concrete-panel-replacement-rehab
- Project type
- Road, bridge and multimodal improvements
Contacts
Recorded professional contact
Kelso Area Engineering Office | (360) 905-1599 | swkelso@wsdot.wa.gov
Recorded contact information. Current role and contact reachability have not been independently rechecked; confirm through the linked source before outreach.
Recorded contact source ↗Source check recorded: 2026-11-06
Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.
Opportunities & Contracts
No procurement verified
No linked, currently verified solicitation has been established for this project.
Previously recorded anticipated work
Planned agency procurement milestones; these are not verified open solicitations or bid deadlines. Spring 2027: Project goes to competitive bidding
Companies Involved
Specific roles and award relationships remain subject to source verification.
Budget & Funding
- Reported project value
- $4,075,285 estimated project cost
- Recorded funding
- Agency funding detail (2026-11-06): Estimated project cost: $4,075,285 and is funded by state and federal funding sources.
Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.
Timeline & Milestones
- Recorded construction start
- Fall 2027: Construction scheduled to begin
- Recorded completion
- Late 2027: Construction scheduled for completion
- Recorded milestones
- Agency-listed project timeline: Fall 2027 - Late 2027. Agency stage: Pre-construction.
Agency milestone schedule (reviewed 2026-11-06):
Summer 2026 - Winter 2026: Review and planning process
Spring 2027: Design completion
Spring 2027: Project goes to competitive bidding
Fall 2027: Construction scheduled to begin
Late 2027: Construction scheduled for completion
Documents & Resources
- WSDOT official project page ↗Reviewed 2026-11-06
Updates & Intelligence
Earlier recorded updates
2026-11-06: Newly indexed from the agency project page. Agency-listed project timeline: Fall 2027 - Late 2027. Agency stage: Pre-construction. Procurement availability has not been verified.
2026-11-06: Official-source enrichment added or expanded contacts, milestones, funding, start, completion, upcoming bids, scope. Planned procurement milestones do not establish an open bid.
Detailed research and a source-backed change history are being assembled. A routine source check is not a material project update.