Sturgeon Bay Harbor maintenance dredging
Sturgeon Bay, Door County, Wisconsin · Ports and maritime, Transportation
Material research update: 2026-11-26 · Source research checked: 2026-11-26
Saved projects appear in your existing research workspace. Saving does not change email preferences.
- Project owner
- U.S. Army Corps of Engineers, Chicago District
- Delivery method
- Awarded task order W912P627FA002 to Roen Salvage Company. Fieldwork is pending.
- Expected completion
- August 31, 2027 (estimated end of fieldwork; Corps planning schedule, updated November 25, 2026)
Overview
Mechanical dredging of about 80,000 cubic yards from the federal navigation channel, with upland placement expected at the Sturgeon Bay Utilities site.
- Additional scope
- Mechanical dredging of about 80,000 cubic yards from the federal navigation channel, with upland placement expected at the Sturgeon Bay Utilities site.
Verified · Corps consistency determination ↗ · Checked 2026-11-26
- Project type
- Federal navigation channel maintenance
Contacts
Project contact research is not yet verified. Use the official agency contact route while research is completed.
Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.
Opportunities & Contracts
No procurement verified
No linked, currently verified solicitation has been established for this project.
Companies Involved
U.S. Army Corps of Engineers ↗
Awarding agency
Federal agency that awarded the order.
Verified · U.S. Army Corps of Engineers ↗ · Source 2026-11-24 · Checked 2026-11-26
Roen Salvage Company ↗
Awarded dredging contractor
Awarded task order W912P627FA002 on November 24, 2026.
Verified · U.S. Army Corps of Engineers ↗ · Source 2026-11-24 · Checked 2026-11-26
Sturgeon Bay Utilities ↗
Planned upland placement site operator
The district identifies the utility site for upland placement.
Verified · U.S. Army Corps of Engineers ↗ · Checked 2026-11-26
Budget & Funding
- Reported project value
- $2,133,900 awarded task order; whole-program cost undisclosed.
- Recorded funding
- The Corps describes the package as FY2025-funded with a planned FY2027 award.
Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.
Timeline & Milestones
- Recorded construction start
- June 2, 2027 (estimated field start; Corps planning schedule, updated November 25, 2026)
- Recorded completion
- August 31, 2027 (estimated end of fieldwork; Corps planning schedule, updated November 25, 2026)
- Recorded milestones
- 2026-11-24 | Task order W912P627FA002 awarded. June 2, 2027 is the estimated start.
Documents & Resources
Primary source
Verified · Corps awarded contracts ↗ · Source 2026-11-24 · Checked 2026-11-26
Primary source
Verified · Corps five-year schedule ↗ · Source 2026-11-25 · Checked 2026-11-26
Primary source
Verified · Corps consistency determination ↗ · Checked 2026-11-26
Primary source
Verified · Roen Salvage project history ↗ · Checked 2026-11-26
Updates & Intelligence
Earlier recorded updates
The Corps estimates June 2 to August 31, 2027 for fieldwork.