Strawberry High Line Canal Lateral 34 Piping

Southern Utah County, Utah

Estimated value$4M
StageNot verified
Owner / developerStrawberry High Line Canal Company
Last verified2026-10-25

Project overview

Reclamation's FY2025 selection identifies work by Strawberry High Line Canal Company in Southern Utah County, Utah: Replace approximately 20,000 feet of concrete-lined open lateral with a pressurized high-density polyethylene pipeline, new turnout gates and flow meters.

Scope
Replace approximately 20,000 feet of concrete-lined open lateral with a pressurized high-density polyethylene pipeline, new turnout gates and flow meters.
Project type
Irrigation pipeline conversion
Reported investment / scope
$3,996,224 (total project cost reported in the FY2025 selection)
Funding sources
Bureau of Reclamation WaterSMART FY2025 selection: $1,998,112 in Reclamation funding. Announced June 3, 2026. Other funding sources and financial closing are not specified in the cited selection.
Delivery method
Not available

Organizations involved

Owner / developer
Strawberry High Line Canal Company
Developer
Not available
Engineering firm / architect
Not available
General contractor / construction manager
Not available
EPC contractor
Not available
Technology / equipment providers
Not available
Financial sponsor
Not available
Other recorded participants
Strawberry High Line Canal Company; U.S. Bureau of Reclamation

Business opportunities

Not verified

Current procurement record
Not available
Upcoming procurement
Not available
Contract / package value
Not available
Supplier / subcontractor opportunities
Not available
Workforce requirements
Not available

Check official project / procurement portal ↗

A project listing is not an open solicitation. Check the source for eligibility, current status, closing time and addenda.

Timeline & key dates

Expected procurement
Not available
Construction start
Not available
Estimated completion
Not available
Dated milestones
2026-06-03: Reclamation announced FY2025 Water and Energy Efficiency Grant selections.
Permitting
Not available
Recent project updates
2026-10-25: Verified against the Bureau of Reclamation’s FY2025 Water and Energy Efficiency Grant selections, announced June 3, 2026. Funding selection verifies the listed scope and financial amounts; it does not establish current construction progress, procurement status, contractor awards or a completion date. These fields remain unverified. No project coordinates were established from this source.
Challenges / risks
Not available

Related intelligence

No verified record associations have been entered for this project yet.

Connections use recorded entity IDs and public evidence. Shared keywords do not establish a relationship.

Additional project record

Reclamation's FY2025 selection identifies work by Strawberry High Line Canal Company in Southern Utah County, Utah: Replace approximately 20,000 feet of concrete-lined open lateral with a pressurized high-density polyethylene pipeline, new turnout gates and flow meters.

Project scope

Replace approximately 20,000 feet of concrete-lined open lateral with a pressurized high-density polyethylene pipeline, new turnout gates and flow meters.

Sponsor and location

Reported organization: Strawberry High Line Canal Company

Location: Southern Utah County, Utah

Reported funding

$3,996,224 (total project cost reported in the FY2025 selection)

Bureau of Reclamation WaterSMART FY2025 selection: $1,998,112 in Reclamation funding. Announced June 3, 2026. Other funding sources and financial closing are not specified in the cited selection.

Status and schedule

2026-10-25: Verified against the Bureau of Reclamation’s FY2025 Water and Energy Efficiency Grant selections, announced June 3, 2026. Funding selection verifies the listed scope and financial amounts; it does not establish current construction progress, procurement status, contractor awards or a completion date. These fields remain unverified. No project coordinates were established from this source.

Source verification

Bureau of Reclamation, FY2025 Water and Energy Efficiency Grant selections, announced June 3, 2026. Source entry: Strawberry High Line Canal Company, Strawberry High Line Canal Lateral 34 Piping Project. Checked October 25, 2026.

Reclamation FY2025 Water and Energy Efficiency Grant selections (PDF)

WaterSMART program announcement and selection information

Saved searches & recent searches

Sign in to keep searches across devices. Your recent searches on this device appear below.

Join Infraday Free · Sign in
You’re offline. Reconnect to load the latest Infraday updates.