SR 504 South Coldwater Slide – Spirit Lake Outlet Bridge Washout

Cowlitz County, Skamania County, Washington · Transportation, Highways and bridges

Stage: ConstructionProcurement: No procurement verified

Source research checked: 2026-11-06

Saved projects appear in your existing research workspace. Saving does not change email preferences.

Recorded project valueNot verified
Construction estimateNot separately verified
Recorded procurement milestoneNot verifiedSee the source and current procurement status.
Construction startNot verified
Project owner
Washington State Department of Transportation
Delivery method
Not verified
Expected completion
Not verified

Overview

Rebuild the landslide-damaged SR 504 roadway and Spirit Lake Outlet Bridge to restore access toward Johnston Ridge Observatory.

Technical scope

Rebuild the landslide-damaged SR 504 roadway and Spirit Lake Outlet Bridge to restore access toward Johnston Ridge Observatory.

Agency-published project contact: Columbia Gorge Area Engineering Office | swGorge@wsdot.wa.gov
Contact source: https://wsdot.wa.gov/construction-planning/search-projects/sr-504-south-coldwater-slide-spirit-lake-outlet-bridge-washout

Project type
Road, bridge and multimodal improvements

Contacts

Recorded professional contact

Columbia Gorge Area Engineering Office | swGorge@wsdot.wa.gov

Recorded contact information. Current role and contact reachability have not been independently rechecked; confirm through the linked source before outreach.

Recorded contact source ↗

Source check recorded: 2026-11-06

Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.

Opportunities & Contracts

No procurement verified

No linked, currently verified solicitation has been established for this project.

Recorded package values
$2.63 million awarded contract

Companies Involved

Recorded contractor
Farline Bridge

Specific roles and award relationships remain subject to source verification.

Budget & Funding

Recorded funding
$2.63 million contract awarded to Farline Bridge using state and federal funds; this amount is not represented as total restoration cost.
Agency funding detail (2026-11-06): Awarded contract: $2.63 million to Farline Bridge. Funding combines state and federal sources.

Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.

Timeline & Milestones

Recorded milestones
Agency-listed project timeline: May 2023 - Spring 2027. Agency stage: Construction.
Agency milestone schedule (reviewed 2026-11-06):
May 14, 2023: A debris slide washed out a portion of the highway and bridge at milepost 49.0.
May 15, 2023: The upper section of SR 504 closed at milepost 43.0.
June 16, 2023: Closure point of SR 504 was moved the winter gate (milepost 45.2) and remained closed to the public in 2023.
June 26, 2023: Emergency contract work started for initial clean up and vehicle recovery.
July 2023: WSDOT teams began design work for a permanent bridge and roadway replacement. A temporary bypass was installed on SR 504.
July 14, 2023: Stranded vehicles were recovered from the Johnston Ridge Observatory.
July 26, 2023: Emergency contract work completed to remove debris and install replacement culverts and a temporary bypass road.
Nov. 5, 2023: Temporary bypass failed. Public access closed at the winter gate, milepost 45.2, until permanent bridge can be completed.
Nov. 17, 2023: Emergency contract work started to remove all temporary bypass infrastructure after discovering the failing culverts.
May 2023 - Summer 2025: WSDOT teams working on pre-design, hydraulics, geotechnical, bridge engineering, and environmental review phases of project development
March 3, 2026: Project contract is advertised and awarded to Farline Bridge, Inc.
April 27, 2026: Construction of the bridge replacement begins.
Spring 2027: The WSDOT road construction project is expected to be completed. U.S. Forest Service will begin restoration of the Observatory.
Spring 2027: The upper portion of SR 504 and the Johnston Ridge Observatory expected to reopen to the public.

Documents & Resources

Updates & Intelligence

Earlier recorded updates

2026-11-06: Newly indexed from the agency project page. Agency-listed project timeline: May 2023 - Spring 2027. Agency stage: Construction. Procurement availability has not been verified.
2026-11-06: Official-source enrichment added or expanded contacts, milestones, funding, contractor, package value, scope. Planned procurement milestones do not establish an open bid.

Detailed research and a source-backed change history are being assembled. A routine source check is not a material project update.