SR 105 – Graveyard Spit Project – Dynamic Revetment and Dune Restoration
Pacific County, Washington · Resilience and flood protection
Source research checked: 2026-11-06
Saved projects appear in your existing research workspace. Saving does not change email preferences.
- Project owner
- Washington State Department of Transportation
- Delivery method
- Not verified
- Expected completion
- Feb. 2027: Construction scheduled for completion
Overview
Protect SR 105 and the Shoalwater Bay community through dune restoration and a wave-absorbing rock barrier at Graveyard Spit, with seasonal wildlife restrictions.
Technical scope
Protect SR 105 and the Shoalwater Bay community through dune restoration and a wave-absorbing rock barrier at Graveyard Spit, with seasonal wildlife restrictions.
Agency-published project contact: Kelso Area Engineering Office | (360) 905-1599 | swkelso@wsdot.wa.gov
Contact source: https://wsdot.wa.gov/construction-planning/search-projects/sr-105-graveyard-spit-project-dynamic-revetment-and-dune-restoration
- Project type
- Erosion protection and resilience
Contacts
Recorded professional contact
Kelso Area Engineering Office | (360) 905-1599 | swkelso@wsdot.wa.gov
Recorded contact information. Current role and contact reachability have not been independently rechecked; confirm through the linked source before outreach.
Recorded contact source ↗Source check recorded: 2026-11-06
Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.
Opportunities & Contracts
No procurement verified
No linked, currently verified solicitation has been established for this project.
Companies Involved
Specific roles and award relationships remain subject to source verification.
Budget & Funding
- Recorded funding
- WSDOT identifies approximately $28 million in federal grants plus $15 million in state funding.
Agency funding detail (2026-11-06): The source reports approximately $28 million of federal grants plus $15 million of state funds. It separately lists about $15.2 million from FEMA, $10 million from NFWF and $4 million from NOAA. Those rounded components do not reconcile exactly with the stated federal total.
Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.
Timeline & Milestones
- Recorded construction start
- July 2025: Construction start
- Recorded completion
- Feb. 2027: Construction scheduled for completion
- Recorded milestones
- Agency-listed project timeline: March 2025 - Feb. 2027. Agency stage: Construction.
Agency milestone schedule (reviewed 2026-11-06):
April 2025: Project went to competitive bidding
July 2025: Construction start
March 2026: Construction on season pause
Oct. 2026: Construction resumed
Feb. 2027: Construction scheduled for completion
Documents & Resources
- WSDOT official project page ↗Reviewed 2026-11-06
Updates & Intelligence
Earlier recorded updates
2026-11-06: Newly indexed from the agency project page. Agency-listed project timeline: March 2025 - Feb. 2027. Agency stage: Construction. Procurement availability has not been verified.
2026-11-06: Official-source enrichment added or expanded contacts, milestones, funding, start, completion, scope. Planned procurement milestones do not establish an open bid.
Detailed research and a source-backed change history are being assembled. A routine source check is not a material project update.