Route 29 (Wards Road) and Route 699 (Gladys Road) intersection improvement project
Campbell County, Virginia · Transportation, Highways and bridges
Source research checked: 2026-11-06
Saved projects appear in your existing research workspace. Saving does not change email preferences.
- Project owner
- Virginia Department of Transportation
- Delivery method
- Not verified
- Expected completion
- Fall 2026
Overview
Reconfigure the Route 29/Gladys Road intersection with a restricted-crossing U-turn layout, raised islands, drainage work and relocated warning flashers.
Technical scope
Reconfigure the Route 29/Gladys Road intersection with a restricted-crossing U-turn layout, raised islands, drainage work and relocated warning flashers.
Agency project references: UPC: 115488; State ID: 6029-015-825, P101; Federal ID: NHPP-015-3(100).
Agency-published project contact: Anthony W. Revelle, P.E. | Project manager | anthony.revelle@vdot.virginia.gov | 434-856-8258
Contact source: https://www.vdot.virginia.gov/projects/lynchburg-district/route-29-wards-road-and-route-699-gladys-road-intersection-improvement-project/
- Project type
- Road, bridge and multimodal improvements
Contacts
Recorded professional contact
Anthony W. Revelle, P.E. | Project manager | anthony.revelle@vdot.virginia.gov | 434-856-8258
Recorded contact information. Current role and contact reachability have not been independently rechecked; confirm through the linked source before outreach.
Recorded contact source ↗Source check recorded: 2026-11-06
Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.
Opportunities & Contracts
No procurement verified
No linked, currently verified solicitation has been established for this project.
Companies Involved
Specific roles and award relationships remain subject to source verification.
Budget & Funding
- Reported project value
- $5.4 Million (agency estimate)
Agency cost detail (2026-11-06): Construction contract value: $3,236,739. Components are not separate contract awards.
Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.
Timeline & Milestones
- Recorded construction start
- Fall 2025
- Recorded completion
- Fall 2026
- Recorded milestones
- Agency status: Under construction. Agency schedule entry: Fall 2025. Estimated completion: Fall 2026.
Agency public-involvement record: Willingness public hearing A willingness public hearing about this project will be held on Tuesday, April 4, 2023, from 4-6 p.m. at the Altavista Train Station, 414 Washington St., Altavista, VA 24517. Route 29 and Route 699 Improvement Project 4-page Brochure TwoColumnAdRoute29and699Intersection
Documents & Resources
- Virginia Department of Transportation official project page ↗Reviewed 2026-11-06
Updates & Intelligence
Earlier recorded updates
2026-11-06: Newly indexed from the agency project page. Agency status: Under construction. Agency schedule entry: Fall 2025. Estimated completion: Fall 2026. Procurement availability has not been verified.