INFRADAY PROJECTS · A00210058; CSJ 0472-01-054

SH 21 Highway Improvement from 0.292 MI E of SL 150 to 0.1 MI E of County Rd. (Bastrop County; TxDOT 0472-01-054)

Bastrop County, Texas · Transportation, Highways and bridges

Stage: PS&E; Construction begins within 4 yearsProcurement: Planned / Forecast

Material research update: 2026-11-20 · Source research checked: 2026-11-20

Saved projects appear in your existing research workspace. Saving does not change email preferences.

Recorded project valueNot verified
Construction estimateUSD 2,074,525
Forecast letting2028-03-07Estimated letting; not advertisement or construction start.
Construction startNot verified
Project owner
Texas Department of Transportation (programming agency)
Delivery method
TxDOT letting classification: Statewide Let.
Expected completion
Not verified

Overview

Highway Improvement on SH 21 from 0.292 MI E of SL 150 to 0.1 MI E of County Rd. in Bastrop County, Texas.

Agency project reference
A00210058; CSJ 0472-01-054

Verified · Texas Department of Transportation ↗ · Source 2025-04-11 · Checked 2026-11-15

Additional scope
Highway Improvement. SH 21; 0.292 MI E of SL 150 to 0.1 MI E of County Rd.

Verified · Texas Department of Transportation ↗ · Source 2025-04-11 · Checked 2026-11-15

Project type
Highway Improvement
Recorded constraints and uncertainties
Project intelligence: an open solicitation and bid deadline have not been verified. Confirm the current procurement route, package scope and dates with the agency before pursuing a contract.

Contacts

Kyle Johnson

TxDOT project contact · Texas Department of Transportation

Public project-information contact identified by the agency. Use the designated bidding channel once a solicitation is issued.

512 3084493

Verified · Texas Department of Transportation ↗ · Source 2025-04-11 · Checked 2026-11-15

Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.

Opportunities & Contracts

Planned / Forecast

This agency project record does not establish a currently open solicitation, a bid deadline or a specific unawarded contract package.

Recorded package values
USD 2,074,525 estimated construction cost. This is a construction estimate, not an awarded contract or a verified total development budget.

Additional scope-based business-development research is available with authorized Infraday+ access.

Companies Involved

Recorded organizations
Texas Department of Transportation (programming agency); TxDOT district: Austin; planning organization: Capital Area

Specific roles and award relationships remain subject to source verification.

Budget & Funding

MeaningAmountBasis
Construction estimateUSD 2,074,525TxDOT project record updated 2025-04-11; not a total project budget or available contract value

Projected · Texas Department of Transportation ↗ · Source 2025-04-11 · Checked 2026-11-15

Funding allocation: 1 - Preventive Maintenance And RehabilitationUSD 2,157,506TxDOT funding category allocation; not contract award or actual spending

Reported · Texas Department of Transportation ↗ · Source 2025-04-11 · Checked 2026-11-15

Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.

Timeline & Milestones

2028-03-07

Estimated letting (not advertisement or construction start)

Projected; confirm current schedule

Projected · Texas Department of Transportation ↗ · Source 2025-04-11 · Checked 2026-11-15

Documents & Resources

Updates & Intelligence

Verified research changes

TxDOT program and delivery detail

TxDOT program funding categories: 1 - Preventive Maintenance And Rehabilitation ($2,157,506).

Change source ↗

Official-source research expanded

Added source-attributed project details. This enrichment is a research event, not a newly announced project, solicitation or award.

Change source ↗
Earlier recorded updates

2026-11-15: Added from official agency inventory. TxDOT reports status Active and stage PS&E; planning category: Construction begins within 4 years. Record last updated 2025-04-11; inventory data updated November 15, 2026. Planned letting is a schedule milestone, not evidence of an open bid.