← Infraday Projects

INFRADAY PROJECTS · A00206754; CSJ 0353-05-135

SS 244 Construct Pedestrian Infrastructure from Lake Highlands Dr. to SH-78 (Garland Rd.) (Dallas County; TxDOT 0353-05-135)

Dallas County, Texas · Transportation

Stage: Planning; Construction begins within 4 yearsProcurement: Planned / Forecast

Material research update: 2026-11-20 · Source research checked: 2026-11-20

Saved projects appear in your existing research workspace. Saving does not change email preferences.

Recorded project valueNot verified
Construction estimateUSD 2,298,243
Forecast letting2027-08-04Estimated letting; not advertisement or construction start.
Construction startNot verified
Project owner
Texas Department of Transportation (programming agency)
Delivery method
TxDOT letting classification: Statewide Let.
Expected completion
Not verified

Overview

Construct Pedestrian Infrastructure on SS 244 from Lake Highlands Dr. to SH-78 (Garland Rd.) in Dallas County, Texas.

Agency project reference
A00206754; CSJ 0353-05-135

Verified · Texas Department of Transportation ↗ · Source 2026-10-08 · Checked 2026-11-15

Additional scope
Construct Pedestrian Infrastructure. SS 244; Lake Highlands Dr. to SH-78 (Garland Rd.)

Verified · Texas Department of Transportation ↗ · Source 2026-10-08 · Checked 2026-11-15

Project type
Construct Pedestrian Infrastructure
Recorded constraints and uncertainties
Project intelligence: an open solicitation and bid deadline have not been verified. Confirm the current procurement route, package scope and dates with the agency before pursuing a contract.

Contacts

Luis Alvarez

TxDOT project contact · Texas Department of Transportation

Public project-information contact identified by the agency. Use the designated bidding channel once a solicitation is issued.

214 3206284

Verified · Texas Department of Transportation ↗ · Source 2026-10-08 · Checked 2026-11-15

Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.

Opportunities & Contracts

Planned / Forecast

This agency project record does not establish a currently open solicitation, a bid deadline or a specific unawarded contract package.

Recorded package values
USD 2,298,243 estimated construction cost. This is a construction estimate, not an awarded contract or a verified total development budget.

Additional scope-based business-development research is available with authorized Infraday+ access.

Companies Involved

Recorded organizations
Texas Department of Transportation (programming agency); TxDOT district: Dallas; planning organization: North Central Texas Council of Governments

Specific roles and award relationships remain subject to source verification.

Budget & Funding

MeaningAmountBasis
Construction estimateUSD 2,298,243TxDOT project record updated 2026-10-08; not a total project budget or available contract value

Projected · Texas Department of Transportation ↗ · Source 2026-10-08 · Checked 2026-11-15

Funding allocation: 1 - Preventive Maintenance And RehabilitationUSD 722,706TxDOT funding category allocation; not contract award or actual spending

Reported · Texas Department of Transportation ↗ · Source 2026-10-08 · Checked 2026-11-15

Funding allocation: 8 - SafetyUSD 1,775,537TxDOT funding category allocation; not contract award or actual spending

Reported · Texas Department of Transportation ↗ · Source 2026-10-08 · Checked 2026-11-15

Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.

Timeline & Milestones

2027-08-04

Estimated letting (not advertisement or construction start)

Projected; confirm current schedule

Projected · Texas Department of Transportation ↗ · Source 2026-10-08 · Checked 2026-11-15

Documents & Resources

Updates & Intelligence

Verified research changes

TxDOT program and delivery detail

TxDOT program funding categories: 1 - Preventive Maintenance And Rehabilitation ($722,706.34), 8 - Safety ($1,775,537). Latest reported design or letting milestone: 2026-05-01 | Design started (TxDOT actual milestone).

Change source ↗

Official-source research expanded

Added source-attributed project details. This enrichment is a research event, not a newly announced project, solicitation or award.

Change source ↗
Earlier recorded updates

2026-11-15: Added from official agency inventory. TxDOT reports status Active and stage Planning; planning category: Construction begins within 4 years. Record last updated 2026-10-08; inventory data updated November 15, 2026. Planned letting is a schedule milestone, not evidence of an open bid.
2026-11-20 | TxDOT program funding categories: 1 - Preventive Maintenance And Rehabilitation ($722,706.34), 8 - Safety ($1,775,537). Latest reported design or letting milestone: 2026-05-01 | Design started (TxDOT actual milestone).

You’re offline. Reconnect to load the latest Infraday updates.