INFRADAY PROJECTS · 79467

SR 12 Elizabeth Avenue — Berks County (PennDOT MPMS 79467)

Berks County, Pennsylvania · Transportation

Stage: ActiveProcurement: Planned / Forecast

Material research update: 2026-11-20 · Source research checked: 2026-11-20

Saved projects appear in your existing research workspace. Saving does not change email preferences.

Recorded project valueNot verified
Construction estimateNot separately verified
Forecast letting2028-06-29Estimated letting; not advertisement or construction start.
Construction startNot verified
Project owner
Pennsylvania Department of Transportation (programming agency)
Delivery method
Not verified
Expected completion
Estimated 2030-12-30

Overview

Safety Improvements include shoulder widening, utility relocation, additional left turn lanes with possible roundabouts at each termini. Intersection of Route 12 and Hill View Road/Elizabeth Ave. and along the Route 12 Corridor from Hill View Road/Elizabeth Ave. to Skyline Drive Alsace Township Berks County

Technical scope

Safety Improvements include shoulder widening, utility relocation, additional left turn lanes with possible roundabouts at each termini. Intersection of Route 12 and Hill View Road/Elizabeth Ave. and along the Route 12 Corridor from Hill View Road/Elizabeth Ave. to Skyline Drive Alsace Township Berks County
One of 3 PennDOT project map points: 40.38877, -75.87724. PennDOT route identifiers: 12, 2016, 2027.

Agency project reference
79467

Verified · Pennsylvania Department of Transportation ↗ · Checked 2026-11-15

Additional scope
Safety Improvements include shoulder widening, utility relocation, additional left turn lanes with possible roundabouts at each termini

Verified · Pennsylvania Department of Transportation ↗ · Checked 2026-11-15

Constraints
Intersection of Route 12 and Hill View Road/Elizabeth Ave. and along the Route 12 Corridor from Hill View Road/Elizabeth Ave. to Skyline Drive
Alsace Township
Berks County

Verified · Pennsylvania Department of Transportation ↗ · Checked 2026-11-15

Funding status
TIP approval: Y; STIP approval: Y; Twelve-Year Program approval: Y; Obligation indicator: Y. Inventory indicators do not establish an award or cash availability.

Verified · Pennsylvania Department of Transportation ↗ · Checked 2026-11-15

Project type
Safety Improvement
Recorded constraints and uncertainties
Project intelligence: an open solicitation and bid deadline have not been verified. Confirm the current procurement route, package scope and dates with the agency before pursuing a contract.

Contacts

Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.

Opportunities & Contracts

Planned / Forecast

This agency project record does not establish a currently open solicitation, a bid deadline or a specific unawarded contract package.

Additional scope-based business-development research is available with authorized Infraday+ access.

Companies Involved

Recorded organizations
Pennsylvania Department of Transportation (programming agency); PennDOT district: 05; planning partner: Reading

Specific roles and award relationships remain subject to source verification.

Budget & Funding

MeaningAmountBasis
Estimated phase costUSD 13,400,000PennDOT phase estimate; phase boundary is not identified by this response. Do not treat as whole-project budget or bid value.

Projected · Pennsylvania Department of Transportation ↗ · Checked 2026-11-15

Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.

Timeline & Milestones

Documents & Resources

Updates & Intelligence

Verified research changes

PennDOT project map and program detail

PennDOT marks project inclusion as approved in the Transportation Improvement Program, Statewide Transportation Improvement Program, Twelve Year Program. One of 3 PennDOT project map points: 40.38877, -75.87724. PennDOT route identifiers: 12, 2016, 2027.

Change source ↗

Official-source research expanded

Added source-attributed project details. This enrichment is a research event, not a newly announced project, solicitation or award.

Change source ↗
Earlier recorded updates

2026-11-15: Added from official agency inventory. PennDOT lists this project as Active in its Four Year Plan map layer. The agency does not expose a record-update date in this response. Retrieved November 15, 2026. Program inclusion does not establish an open solicitation.
2026-11-20 | PennDOT marks project inclusion as approved in the Transportation Improvement Program, Statewide Transportation Improvement Program, Twelve Year Program. One of 3 PennDOT project map points: 40.38877, -75.87724. PennDOT route identifiers: 12, 2016, 2027.