HBX1190 Grand Concourse Bridge over Metro North Railroad Hudson Line — Bronx (NYC HBX1190)

Bronx, New York City, New York · Transportation, Highways and bridges

Stage: Construction (May 2026 reporting period)Procurement: No procurement verified

Material research update: 2026-11-20 · Source research checked: 2026-11-20

Saved projects appear in your existing research workspace. Saving does not change email preferences.

Recorded project valueUSD 93,354,294 — City total-budget/commitments field; May 2026 reporting period
Construction estimateNot separately verified
Recorded procurement milestoneNot verifiedSee the source and current procurement status.
Construction startReported construction start: 2020-05-18
Project owner
NYC Department of Transportation (managing agency)
Delivery method
Not verified
Expected completion
Forecast 2027-11-22 in May 2026 report; not a guaranteed delivery date

Overview

The Grand Concourse Bridge carries four lanes of vehicular traffic and three NYC Transit No. 4 tracks beneath the roadway structure. The Metro-North Railroad Hudson line runs under the Grand Concourse Bridge. This project will completely replace the roadway bridge structure which was last rehabilitated in 1982 and originally constructed in 1906 (subway structure added in 1917). Replacement of the deteriorated…

Technical scope

The Grand Concourse Bridge carries four lanes of vehicular traffic and three NYC Transit No. 4 tracks beneath the roadway structure. The Metro-North Railroad Hudson line runs under the Grand Concourse Bridge. This project will completely replace the roadway bridge structure which was last rehabilitated in 1982 and originally constructed in 1906 (subway structure added in 1917). Replacement of the deteriorated subway structural elements will also be a part of this project. In addition to the bridge work, the project will also incorporate the following pedestrian improvements which are consistent with NYC’s Vision Zero and OneNYC objectives:• Curb extensions will be added at street corners to reduce the pedestrian crossing distance at both 151st and 153rd Streets and sidewalk limits will be generally be expanding throughout the project limits.• The raised concrete median in the center of Grand Concourse will be widened which will reduce pedestrian crossing distance while also creating space for a future bicycle lane.• ADA compliant pedestrian ramps will be installed at all pedestrian crossing within the project limits along with high-visibility crosswalks.• The Grand Concourse northbound 153rd Street MTA bus stop concrete island will be expanded while maintaining existing bush and tree plantings.• Street lighting was re-analyzed and the proposed design will improve on the existing lighting conditions. All new street lights will have LED luminaires installed as well as any existing street lights that are remaining. The proposed street lights will use historic Type M poles and luminaires to match the aesthetics of the Grand Concourse Historic District.

Agency project reference
DOT / 2079; FMS HBX1190

Verified · New York City Capital Projects Dashboard ↗ · Source 2026-06-29 · Checked 2026-11-15

Additional scope
The Grand Concourse Bridge carries four lanes of vehicular traffic and three NYC Transit No. 4 tracks beneath the roadway structure. The Metro-North Railroad Hudson line runs under the Grand Concourse Bridge. This project will completely replace the roadway bridge structure which was last rehabilitated in 1982 and originally constructed in 1906 (subway structure added in 1917). Replacement of the deteriorated subway structural elements will also be a part of this project. In addition to the bridge work, the project will also incorporate the following pedestrian improvements which are consistent with NYC’s Vision Zero and OneNYC objectives:• Curb extensions will be added at street corners to reduce the pedestrian crossing distance at both 151st and 153rd Streets and sidewalk limits will be generally be expanding throughout the project limits.• The raised concrete median in the center of Grand Concourse will be widened which will reduce pedestrian crossing distance while also creating space for a future bicycle lane.• ADA compliant pedestrian ramps will be installed at all pedestrian crossing within the project limits along with high-visibility crosswalks.• The Grand Concourse northbound 153rd Street MTA bus stop concrete island will be expanded while maintaining existing bush and tree plantings.• Street lighting was re-analyzed and the proposed design will improve on the existing lighting conditions. All new street lights will have LED luminaires installed as well as any existing street lights that are remaining. The proposed street lights will use historic Type M poles and luminaires to match the aesthetics of the Grand Concourse Historic District.

Verified · New York City Capital Projects Dashboard ↗ · Source 2026-06-29 · Checked 2026-11-15

Project type
Capital infrastructure project
Recorded constraints and uncertainties
No open solicitation or bid deadline is verified for this record. Confirm procurement requirements with the relevant agency before pursuing a contract.

Contacts

Project contact research is not yet verified. Use the official agency contact route while research is completed.

Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.

Opportunities & Contracts

No procurement verified

This agency project record does not establish a currently open solicitation, a bid deadline or a specific unawarded contract package.

Additional scope-based business-development research is available with authorized Infraday+ access.

Companies Involved

Recorded organizations
NYC Department of Transportation (managing agency); sponsoring agency: NYC Department of Transportation

Specific roles and award relationships remain subject to source verification.

Budget & Funding

MeaningAmountBasis
City reported budget / commitmentsUSD 93,354,294City dashboard May 2026 reporting; FMS data date 2026-05-18; City accounting measure, not an advertised contract value

Reported · New York City Capital Projects Dashboard ↗ · Source 2026-06-29 · Checked 2026-11-15

Reported spending to dateUSD 28,552,750City dashboard May 2026 reporting; FMS data date 2026-05-18

Reported · New York City Capital Projects Dashboard ↗ · Source 2026-06-29 · Checked 2026-11-15

Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.

Timeline & Milestones

Documents & Resources

Updates & Intelligence

Verified research changes

Capital spending and schedule detail

NYC reported $28,552,750.11 spent to date in the May 2026 reporting period (financial data dated 2026-05-18). City capital budget line: HB-1190.

Change source ↗

Official-source research expanded

Added source-attributed project details. This enrichment is a research event, not a newly announced project, solicitation or award.

Change source ↗
Earlier recorded updates

2026-11-15: Added from official agency inventory. The City reported construction as of 2026-06-29 in its May 2026 reporting period. This is a dated capital-project snapshot; subsequent phase changes are not independently verified.
2026-11-20 | NYC reported $28,552,750.11 spent to date in the May 2026 reporting period (financial data dated 2026-05-18). City capital budget line: HB-1190.