INFRADAY PROJECTS · DEP / 675; FMS DEL-415
Valve Replacements at East Delaware Release Chamber (EDRC) — Citywide (NYC DEL-415)
Citywide, New York City, New York · Water and wastewater
Material research update: 2026-11-20 · Source research checked: 2026-11-20
Saved projects appear in your existing research workspace. Saving does not change email preferences.
- Project owner
- NYC Department of Environmental Protection (managing agency)
- Delivery method
- Not verified
- Expected completion
- Forecast 2031-09-15 in May 2026 report; not a guaranteed delivery date
Overview
Replacement of two (2) 42”dia cone valves and two (2) 60” butterfly valves located on the north and south line within the valve chamber of the EDRC in Downsville. The 2 cone valves require replacement to isolate the polyjet regulating Valves. The butterfly valves require replacement due to lack of closure & leakage. Also included will be replacement of the Polyjet Valve Actuators and the 20” Gate Valve on the…
Technical scope
Replacement of two (2) 42”dia cone valves and two (2) 60” butterfly valves located on the north and south line within the valve chamber of the EDRC in Downsville. The 2 cone valves require replacement to isolate the polyjet regulating Valves. The butterfly valves require replacement due to lack of closure & leakage. Also included will be replacement of the Polyjet Valve Actuators and the 20” Gate Valve on the Conservation Line. The valve replacements require the EDRC to be isolated, shutdown and bypassed. The two (2) 42”x60” Venturi on the North & South Release Line and 12”x20” venturi on the Conservation Line are to be removed, inspected, refurbished, and reinstalled.
- Agency project reference
- DEP / 675; FMS DEL-415
Verified · New York City Capital Projects Dashboard ↗ · Source 2026-06-26 · Checked 2026-11-15
- Additional scope
- Replacement of two (2) 42”dia cone valves and two (2) 60” butterfly valves located on the north and south line within the valve chamber of the EDRC in Downsville. The 2 cone valves require replacement to isolate the polyjet regulating Valves. The butterfly valves require replacement due to lack of closure & leakage. Also included will be replacement of the Polyjet Valve Actuators and the 20” Gate Valve on the Conservation Line. The valve replacements require the EDRC to be isolated, shutdown and bypassed. The two (2) 42”x60” Venturi on the North & South Release Line and 12”x20” venturi on the Conservation Line are to be removed, inspected, refurbished, and reinstalled.
Verified · New York City Capital Projects Dashboard ↗ · Source 2026-06-26 · Checked 2026-11-15
- Project type
- Capital infrastructure project
- Recorded constraints and uncertainties
- No open solicitation or bid deadline is verified for this record. Confirm procurement requirements with the relevant agency before pursuing a contract.
Contacts
Project contact research is not yet verified. Use the official agency contact route while research is completed.
Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.
Opportunities & Contracts
No procurement verified
This agency project record does not establish a currently open solicitation, a bid deadline or a specific unawarded contract package.
Companies Involved
- Recorded organizations
- NYC Department of Environmental Protection (managing agency); sponsoring agency: NYC Department of Environmental Protection
Specific roles and award relationships remain subject to source verification.
Budget & Funding
| Meaning | Amount | Basis |
|---|---|---|
| City reported budget / commitments | USD 22,468,400 | City dashboard May 2026 reporting; FMS data date 2026-05-18; City accounting measure, not an advertised contract value Reported · New York City Capital Projects Dashboard ↗ · Source 2026-06-26 · Checked 2026-11-15 |
| Reported spending to date | USD 163,400 | City dashboard May 2026 reporting; FMS data date 2026-05-18 Reported · New York City Capital Projects Dashboard ↗ · Source 2026-06-26 · Checked 2026-11-15 |
Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.
Timeline & Milestones
Reported start of the listed phase
Agency-reported milestone
Verified · New York City Capital Projects Dashboard ↗ · Source 2026-06-26 · Checked 2026-11-15
Forecast end of the listed phase
Projected; confirm current schedule
Projected · New York City Capital Projects Dashboard ↗ · Source 2026-06-26 · Checked 2026-11-15
Forecast project completion
Projected; confirm current schedule
Projected · New York City Capital Projects Dashboard ↗ · Source 2026-06-26 · Checked 2026-11-15
Reported design start
Agency-reported milestone
Verified · New York City Capital Projects Dashboard ↗ · Source 2026-06-26 · Checked 2026-11-15
Documents & Resources
Agency inventory; retrieved 2026-11-15
Verified · New York City Capital Projects Dashboard ↗ · Source 2026-06-26 · Checked 2026-11-15
Updates & Intelligence
Verified research changes
Capital spending and schedule detail
NYC reported $163,400 spent to date in the May 2026 reporting period (financial data dated 2026-05-18). City capital budget line: WM-0030, WM-0030.
Change source ↗Official-source research expanded
Added source-attributed project details. This enrichment is a research event, not a newly announced project, solicitation or award.
Change source ↗Earlier recorded updates
2026-11-15: Added from official agency inventory. The City reported construction procurement as of 2026-06-26 in its May 2026 reporting period. This is a dated capital-project snapshot; subsequent phase changes are not independently verified.
2026-11-20 | NYC reported $163,400 spent to date in the May 2026 reporting period (financial data dated 2026-05-18). City capital budget line: WM-0030, WM-0030.