INFRADAY PROJECTS · DDC / 5731; FMS PW77207RF

1932 Arthur Ave Envelope Stabilization — Bronx (NYC PW77207RF)

Bronx, New York City, New York · Public buildings

Stage: Design (May 2026 reporting period)Procurement: No procurement verified

Material research update: 2026-11-20 · Source research checked: 2026-11-20

Saved projects appear in your existing research workspace. Saving does not change email preferences.

Recorded project valueUSD 60,248,199 — City total-budget/commitments field; May 2026 reporting period
Construction estimateNot separately verified
Recorded procurement milestoneNot verifiedSee the source and current procurement status.
Construction startNot verified
Project owner
NYC Department of Design and Construction (managing agency)
Delivery method
Not verified
Expected completion
Forecast 2029-10-10 in May 2026 report; not a guaranteed delivery date

Overview

The Bergen Building, located in the Tremont area of the Bronx and fronting the main pedestrian entrance of the William Gladwin Park, is composed of two separate adjacent buildings built in 1912 and 1916. In the mid-1930s, the City purchased both buildings and joined them. The building currently is leased to several not-for-profits and city agencies. The Department of Citywide Administrative Services manages and…

Technical scope

The Bergen Building, located in the Tremont area of the Bronx and fronting the main pedestrian entrance of the William Gladwin Park, is composed of two separate adjacent buildings built in 1912 and 1916. In the mid-1930s, the City purchased both buildings and joined them. The building currently is leased to several not-for-profits and city agencies. The Department of Citywide Administrative Services manages and maintains the building. In 2014, DCAS, working with Mayor DeBlasio’s office identified the building as a candidate for significant energy improvements in line with the goals of the OneNYC. The City engaged Studio Gang to conduct a Pre-Schematic Design Report in anticipation of these upgrades, which detailed three levels of proposed energy improvements, bronze, silver and gold, with estimates and ambitious energy performance scope proposals.As part of this analysis, and others, major code compliance issues have been identified on the interior of the building, including travel distances, exit separation, restroom configuration and fixture counts, and accessibility issues. The building’s façade has been deficient for decades and has been determined scientifically to be a mold habitat. The fire alarm system is obsolete. Much of the wiring is original, and there is not enough electric capacity for a new HVAC system. The building requires a new sprinkler standpipe. Previous efforts to initiate Studio Gang’s proposals were underfunded. In the meantime, the building continued to degrade, and most grievously, the envelope lack of watertightness continues to take its toll.Accordingly, priority has been given to the stabilization of the envelope, as the current project initiation request makes clear. There is a budget of almost $40M to make the building watertight by replacing the roof, rehabilitating the masonry, replacing the windows, and installing a rain screen on the most porous surfaces. Critically, DCAS/Real Estate has identified required swing space to enable this work while the building remains open; new scope for this swing is included. There is cross-bracing in the rear yard which requires rehabilitation to address the façade.

Agency project reference
DDC / 5731; FMS PW77207RF

Verified · New York City Capital Projects Dashboard ↗ · Source 2026-06-23 · Checked 2026-11-15

Additional scope
The Bergen Building, located in the Tremont area of the Bronx and fronting the main pedestrian entrance of the William Gladwin Park, is composed of two separate adjacent buildings built in 1912 and 1916. In the mid-1930s, the City purchased both buildings and joined them. The building currently is leased to several not-for-profits and city agencies. The Department of Citywide Administrative Services manages and maintains the building. In 2014, DCAS, working with Mayor DeBlasio’s office identified the building as a candidate for significant energy improvements in line with the goals of the OneNYC. The City engaged Studio Gang to conduct a Pre-Schematic Design Report in anticipation of these upgrades, which detailed three levels of proposed energy improvements, bronze, silver and gold, with estimates and ambitious energy performance scope proposals.As part of this analysis, and others, major code compliance issues have been identified on the interior of the building, including travel distances, exit separation, restroom configuration and fixture counts, and accessibility issues. The building’s façade has been deficient for decades and has been determined scientifically to be a mold habitat. The fire alarm system is obsolete. Much of the wiring is original, and there is not enough electric capacity for a new HVAC system. The building requires a new sprinkler standpipe. Previous efforts to initiate Studio Gang’s proposals were underfunded. In the meantime, the building continued to degrade, and most grievously, the envelope lack of watertightness continues to take its toll.Accordingly, priority has been given to the stabilization of the envelope, as the current project initiation request makes clear. There is a budget of almost $40M to make the building watertight by replacing the roof, rehabilitating the masonry, replacing the windows, and installing a rain screen on the most porous surfaces. Critically, DCAS/Real Estate has identified required swing space to enable this work while the building remains open; new scope for this swing is included. There is cross-bracing in the rear yard which requires rehabilitation to address the façade.

Verified · New York City Capital Projects Dashboard ↗ · Source 2026-06-23 · Checked 2026-11-15

Project type
Capital infrastructure project
Recorded constraints and uncertainties
No open solicitation or bid deadline is verified for this record. Confirm procurement requirements with the relevant agency before pursuing a contract.

Contacts

Project contact research is not yet verified. Use the official agency contact route while research is completed.

Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.

Opportunities & Contracts

No procurement verified

This agency project record does not establish a currently open solicitation, a bid deadline or a specific unawarded contract package.

Additional scope-based business-development research is available with authorized Infraday+ access.

Companies Involved

Recorded organizations
NYC Department of Design and Construction (managing agency); sponsoring agency: NYC Department of Citywide Administrative Services

Specific roles and award relationships remain subject to source verification.

Budget & Funding

MeaningAmountBasis
City reported budget / commitmentsUSD 60,248,199City dashboard May 2026 reporting; FMS data date 2026-05-18; City accounting measure, not an advertised contract value

Reported · New York City Capital Projects Dashboard ↗ · Source 2026-06-23 · Checked 2026-11-15

Reported spending to dateUSD 1,015,225City dashboard May 2026 reporting; FMS data date 2026-05-18

Reported · New York City Capital Projects Dashboard ↗ · Source 2026-06-23 · Checked 2026-11-15

Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.

Timeline & Milestones

Documents & Resources

Updates & Intelligence

Verified research changes

Capital spending and schedule detail

NYC reported $1,015,225.19 spent to date in the May 2026 reporting period (financial data dated 2026-05-18). City capital budget line: PU-0025, PW-0077.

Change source ↗

Official-source research expanded

Added source-attributed project details. This enrichment is a research event, not a newly announced project, solicitation or award.

Change source ↗
Earlier recorded updates

2026-11-15: Added from official agency inventory. The City reported design as of 2026-06-23 in its May 2026 reporting period. This is a dated capital-project snapshot; subsequent phase changes are not independently verified.
2026-11-20 | NYC reported $1,015,225.19 spent to date in the May 2026 reporting period (financial data dated 2026-05-18). City capital budget line: PU-0025, PW-0077.