New Firehouse – Ec268 — Queens (NYC F175EC268)
Queens, New York City, New York · Public buildings
Material research update: 2026-11-20 · Source research checked: 2026-11-20
Saved projects appear in your existing research workspace. Saving does not change email preferences.
- Project owner
- NYC Department of Design and Construction (managing agency)
- Delivery method
- Not verified
- Expected completion
- Forecast 2027-06-24 in May 2026 report; not a guaranteed delivery date
Overview
Design and construct a new double-company fire house in conformance to FDNY design standards and space program. With a programmed area of 13,304 square feet, and an additional need for exterior parking to accommodate 12 vehicles, this facility will replace the old fire house (located at 2-59 Beach 116th Street) which is outdated, inadequate, and was severely damaged during the super storm Sandy of October 2012.
- Agency project reference
- DDC / 3889; FMS F175EC268
Verified · New York City Capital Projects Dashboard ↗ · Source 2026-06-23 · Checked 2026-11-15
- Additional scope
- Design and construct a new double-company fire house in conformance to FDNY design standards and space program. With a programmed area of 13,304 square feet, and an additional need for exterior parking to accommodate 12 vehicles, this facility will replace the old fire house (located at 2-59 Beach 116th Street) which is outdated, inadequate, and was severely damaged during the super storm Sandy of October 2012.
Verified · New York City Capital Projects Dashboard ↗ · Source 2026-06-23 · Checked 2026-11-15
- Project type
- Capital infrastructure project
- Recorded constraints and uncertainties
- No open solicitation or bid deadline is verified for this record. Confirm procurement requirements with the relevant agency before pursuing a contract.
Contacts
Project contact research is not yet verified. Use the official agency contact route while research is completed.
Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.
Opportunities & Contracts
No procurement verified
This agency project record does not establish a currently open solicitation, a bid deadline or a specific unawarded contract package.
Additional scope-based business-development research is available with authorized Infraday+ access.
Companies Involved
- Recorded organizations
- NYC Department of Design and Construction (managing agency); sponsoring agency: Fire Department of the City of New York
Specific roles and award relationships remain subject to source verification.
Budget & Funding
| Meaning | Amount | Basis |
|---|---|---|
| City reported budget / commitments | USD 45,541,224 | City dashboard May 2026 reporting; FMS data date 2026-05-18; City accounting measure, not an advertised contract value Reported · New York City Capital Projects Dashboard ↗ · Source 2026-06-23 · Checked 2026-11-15 |
| Reported spending to date | USD 5,587,968 | City dashboard May 2026 reporting; FMS data date 2026-05-18 Reported · New York City Capital Projects Dashboard ↗ · Source 2026-06-23 · Checked 2026-11-15 |
Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.
Timeline & Milestones
Reported start of the listed phase
Agency-reported milestone
Verified · New York City Capital Projects Dashboard ↗ · Source 2026-06-23 · Checked 2026-11-15
Forecast end of the listed phase
Projected; confirm current schedule
Projected · New York City Capital Projects Dashboard ↗ · Source 2026-06-23 · Checked 2026-11-15
Forecast project completion
Projected; confirm current schedule
Projected · New York City Capital Projects Dashboard ↗ · Source 2026-06-23 · Checked 2026-11-15
Reported design start
Agency-reported milestone
Verified · New York City Capital Projects Dashboard ↗ · Source 2026-06-23 · Checked 2026-11-15
Reported design end
Agency-reported milestone
Verified · New York City Capital Projects Dashboard ↗ · Source 2026-06-23 · Checked 2026-11-15
Documents & Resources
Agency inventory; retrieved 2026-11-15
Verified · New York City Capital Projects Dashboard ↗ · Source 2026-06-23 · Checked 2026-11-15
Updates & Intelligence
Verified research changes
Capital spending and schedule detail
NYC reported $5,587,968.11 spent to date in the May 2026 reporting period (financial data dated 2026-05-18). City capital budget line: F -0175.
Change source ↗Official-source research expanded
Added source-attributed project details. This enrichment is a research event, not a newly announced project, solicitation or award.
Change source ↗Earlier recorded updates
2026-11-15: Added from official agency inventory. The City reported construction as of 2026-06-23 in its May 2026 reporting period. This is a dated capital-project snapshot; subsequent phase changes are not independently verified.
2026-11-20 | NYC reported $5,587,968.11 spent to date in the May 2026 reporting period (financial data dated 2026-05-18). City capital budget line: F -0175.