Bridge 00349 Rehabilitation — Westbrook (CTDOT 0154-0127)

Westbrook, Connecticut · Transportation, Highways and bridges

Stage: Construction (Pending)Procurement: No procurement verified

Material research update: 2026-11-20 · Source research checked: 2026-11-20

Saved projects appear in your existing research workspace. Saving does not change email preferences.

Total project estimateUSD 9,133,403
Construction estimateUSD 7,348,403
Expected advertisement2026-07-15Forecast only; not an open bid
Construction startNot verified
Project owner
Connecticut Department of Transportation (managing agency)
Delivery method
Not verified
Expected completion
Not verified

Overview

Replacement of deck, steel strengthening, and substructure repairs of Bridge No. 00349 (Singing Bridge), which carries US Route 1 over the Patchogue River in Westbrook. FAP 0001(364)

Technical scope

Replacement of deck, steel strengthening, and substructure repairs of Bridge No. 00349 (Singing Bridge), which carries US Route 1 over the Patchogue River in Westbrook. FAP 0001(364)
CTDOT bridge identifiers: 00349.

Agency project reference
0154-0127

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Design progress
100% recorded design completion

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Structures / facilities
00349

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Additional scope
Replacement of deck, steel strengthening, and substructure repairs of Bridge No. 00349 (Singing Bridge), which carries US Route 1 over the Patchogue River in Westbrook. FAP 0001(364)

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Project type
Capital infrastructure project
Recorded constraints and uncertainties
No open solicitation or bid deadline is verified for this record. Confirm procurement requirements with the relevant agency before pursuing a contract.

Contacts

Isuf Vlashi

Project lead engineer · Connecticut Department of Transportation

Public project-information contact identified by the agency. Use the designated bidding channel once a solicitation is issued.

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.

Opportunities & Contracts

No procurement verified

This agency project record does not establish a currently open solicitation, a bid deadline or a specific unawarded contract package.

Additional scope-based business-development research is available with authorized Infraday+ access.

Companies Involved

H & H

Consultant engineer listed by CTDOT

Agency-listed relationship; award date, amount and contract package not independently verified

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

ROTHA Contracting Company Inc

Contractor listed by CTDOT

Agency-listed relationship; award date, amount and contract package not independently verified

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Budget & Funding

MeaningAmountBasis
Total project estimateUSD 9,133,403CTDOT inventory dated 2026-11-04

Projected · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Construction estimateUSD 7,348,403CTDOT inventory dated 2026-11-04

Projected · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Recorded preliminary engineering expenditureUSD 1,485,914CTDOT inventory dated 2026-11-04

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Recorded right-of-way expenditureUSD 34,450CTDOT inventory dated 2026-11-04

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Recorded construction expenditureUSD 7,777CTDOT inventory dated 2026-11-04

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.

Timeline & Milestones

Documents & Resources

Updates & Intelligence

Verified research changes

CTDOT project detail

CTDOT figures as of 2026-11-19: construction estimate $7,348,403, preliminary engineering expenditures $1,486,230, right-of-way expenditures $34,523, construction expenditures $8,991. 2026-11-19 | CTDOT reported design 100% complete. CTDOT bridge identifiers: 00349.

Change source ↗

Official-source research expanded

Added source-attributed project details. This enrichment is a research event, not a newly announced project, solicitation or award.

Change source ↗
Earlier recorded updates

2026-11-15: Added from official agency inventory. CTDOT lists the schedule phase as 05 Construction (Pending). Source snapshot: 2026-11-04. Project estimates and schedules can change. The source labels construction as pending; work underway is not verified.
2026-11-20 | CTDOT figures as of 2026-11-19: construction estimate $7,348,403, preliminary engineering expenditures $1,486,230, right-of-way expenditures $34,523, construction expenditures $8,991. 2026-11-19 | CTDOT reported design 100% complete. CTDOT bridge identifiers: 00349.