PRRP & Lane Reduct – Route 25 — Trumbull (CTDOT 0144-0202)

Trumbull, Connecticut · Transportation

Stage: PlanningProcurement: Planned / Forecast

Material research update: 2026-11-20 · Source research checked: 2026-11-20

Saved projects appear in your existing research workspace. Saving does not change email preferences.

Total project estimateUSD 135,850,000
Construction estimateUSD 118,800,000
Expected advertisement2030-08-14Forecast only; not an open bid
Construction startNot verified
Project owner
Connecticut Department of Transportation (managing agency)
Delivery method
Not verified
Expected completion
Not verified

Overview

Pavement improvements and lane reduction from three travel lanes to two in each direction on Route 25 in Trumbull for approx. 3.7 miles (MPs 5.83-9.52). Noise barrier, guiderail, drainage systems, and overall roadside safety conditions to be upgraded.

Technical scope

Pavement improvements and lane reduction from three travel lanes to two in each direction on Route 25 in Trumbull for approx. 3.7 miles (MPs 5.83-9.52). Noise barrier, guiderail, drainage systems, and overall roadside safety conditions to be upgraded.
CTDOT bridge identifiers: 02928, 04327, 04329, 06750, 02928, 04327, 04329, 06750.

Agency project reference
0144-0202

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Design progress
0% recorded design completion

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Structures / facilities
02928, 04327, 04329, 06750, 02928, 04327, 04329, 06750

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Additional scope
Pavement improvements and lane reduction from three travel lanes to two in each direction on Route 25 in Trumbull for approx. 3.7 miles (MPs 5.83-9.52). Noise barrier, guiderail, drainage systems, and overall roadside safety conditions to be upgraded.

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Project type
Capital infrastructure project
Recorded constraints and uncertainties
No open solicitation or bid deadline is verified for this record. Confirm procurement requirements with the relevant agency before pursuing a contract.

Contacts

Pinith B Mar

Project lead engineer · Connecticut Department of Transportation

Public project-information contact identified by the agency. Use the designated bidding channel once a solicitation is issued.

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.

Opportunities & Contracts

Planned / Forecast

This agency project record does not establish a currently open solicitation, a bid deadline or a specific unawarded contract package.

Additional scope-based business-development research is available with authorized Infraday+ access.

Companies Involved

Recorded organizations
Connecticut Department of Transportation (managing agency)

Specific roles and award relationships remain subject to source verification.

Budget & Funding

MeaningAmountBasis
Total project estimateUSD 135,850,000CTDOT inventory dated 2026-11-04

Projected · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Construction estimateUSD 118,800,000CTDOT inventory dated 2026-11-04

Projected · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Recorded preliminary engineering expenditureUSD 40,919CTDOT inventory dated 2026-11-04

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.

Timeline & Milestones

Documents & Resources

Updates & Intelligence

Verified research changes

CTDOT project detail

CTDOT figures as of 2026-11-19: construction estimate $118,800,000, preliminary engineering expenditures $73,397. 2026-11-19 | CTDOT reported design 0% complete. CTDOT bridge identifiers: 02928, 04327, 04329, 06750, 02928, 04327, 04329, 06750.

Change source ↗

Official-source research expanded

Added source-attributed project details. This enrichment is a research event, not a newly announced project, solicitation or award.

Change source ↗
Earlier recorded updates

2026-11-15: Added from official agency inventory. CTDOT lists the schedule phase as 01 Planning. Source snapshot: 2026-11-04. Project estimates and schedules can change.
2026-11-20 | CTDOT figures as of 2026-11-19: construction estimate $118,800,000, preliminary engineering expenditures $73,397. 2026-11-19 | CTDOT reported design 0% complete. CTDOT bridge identifiers: 02928, 04327, 04329, 06750, 02928, 04327, 04329, 06750.