PRRP & Lane Reduct – Route 25 — Trumbull (CTDOT 0144-0202)
Trumbull, Connecticut · Transportation
Material research update: 2026-11-20 · Source research checked: 2026-11-20
Saved projects appear in your existing research workspace. Saving does not change email preferences.
- Project owner
- Connecticut Department of Transportation (managing agency)
- Delivery method
- Not verified
- Expected completion
- Not verified
Overview
Pavement improvements and lane reduction from three travel lanes to two in each direction on Route 25 in Trumbull for approx. 3.7 miles (MPs 5.83-9.52). Noise barrier, guiderail, drainage systems, and overall roadside safety conditions to be upgraded.
Technical scope
Pavement improvements and lane reduction from three travel lanes to two in each direction on Route 25 in Trumbull for approx. 3.7 miles (MPs 5.83-9.52). Noise barrier, guiderail, drainage systems, and overall roadside safety conditions to be upgraded.
CTDOT bridge identifiers: 02928, 04327, 04329, 06750, 02928, 04327, 04329, 06750.
- Agency project reference
- 0144-0202
Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15
- Design progress
- 0% recorded design completion
Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15
- Structures / facilities
- 02928, 04327, 04329, 06750, 02928, 04327, 04329, 06750
Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15
- Additional scope
- Pavement improvements and lane reduction from three travel lanes to two in each direction on Route 25 in Trumbull for approx. 3.7 miles (MPs 5.83-9.52). Noise barrier, guiderail, drainage systems, and overall roadside safety conditions to be upgraded.
Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15
- Project type
- Capital infrastructure project
- Recorded constraints and uncertainties
- No open solicitation or bid deadline is verified for this record. Confirm procurement requirements with the relevant agency before pursuing a contract.
Contacts
Meredith L Andrews
Project manager · Connecticut Department of Transportation
Public project-information contact identified by the agency. Use the designated bidding channel once a solicitation is issued.
Meredith.Andrews@ct.govVerified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15
Pinith B Mar
Project lead engineer · Connecticut Department of Transportation
Public project-information contact identified by the agency. Use the designated bidding channel once a solicitation is issued.
Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15
Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.
Opportunities & Contracts
Planned / Forecast
This agency project record does not establish a currently open solicitation, a bid deadline or a specific unawarded contract package.
Additional scope-based business-development research is available with authorized Infraday+ access.
Companies Involved
- Recorded organizations
- Connecticut Department of Transportation (managing agency)
Specific roles and award relationships remain subject to source verification.
Budget & Funding
| Meaning | Amount | Basis |
|---|---|---|
| Total project estimate | USD 135,850,000 | CTDOT inventory dated 2026-11-04 Projected · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15 |
| Construction estimate | USD 118,800,000 | CTDOT inventory dated 2026-11-04 Projected · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15 |
| Recorded preliminary engineering expenditure | USD 40,919 | CTDOT inventory dated 2026-11-04 Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15 |
Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.
Timeline & Milestones
Forecast advertisement
Projected; confirm current schedule
Projected · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15
Documents & Resources
Agency inventory; retrieved 2026-11-15
Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15
Updates & Intelligence
Verified research changes
CTDOT project detail
CTDOT figures as of 2026-11-19: construction estimate $118,800,000, preliminary engineering expenditures $73,397. 2026-11-19 | CTDOT reported design 0% complete. CTDOT bridge identifiers: 02928, 04327, 04329, 06750, 02928, 04327, 04329, 06750.
Change source ↗Official-source research expanded
Added source-attributed project details. This enrichment is a research event, not a newly announced project, solicitation or award.
Change source ↗Earlier recorded updates
2026-11-15: Added from official agency inventory. CTDOT lists the schedule phase as 01 Planning. Source snapshot: 2026-11-04. Project estimates and schedules can change.
2026-11-20 | CTDOT figures as of 2026-11-19: construction estimate $118,800,000, preliminary engineering expenditures $73,397. 2026-11-19 | CTDOT reported design 0% complete. CTDOT bridge identifiers: 02928, 04327, 04329, 06750, 02928, 04327, 04329, 06750.