Rehab Bridge #07054 (Culvert) — Middlebury, Southbury (CTDOT 0130-0191)

Middlebury, Southbury, Connecticut · Transportation, Highways and bridges

Stage: Pre DesignProcurement: Planned / Forecast

Material research update: 2026-11-20 · Source research checked: 2026-11-20

Saved projects appear in your existing research workspace. Saving does not change email preferences.

Total project estimateUSD 8,382,500
Construction estimateUSD 7,350,000
Expected advertisement2029-08-08Forecast only; not an open bid
Construction startNot verified
Project owner
Connecticut Department of Transportation (managing agency)
Delivery method
Not verified
Expected completion
Not verified

Overview

Rehabilitation of Bridge No. 07054 (culvert) conveying Eight Mile Brook under Interstate 84 (I-84) in the Town of Southbury.

Technical scope

Rehabilitation of Bridge No. 07054 (culvert) conveying Eight Mile Brook under Interstate 84 (I-84) in the Town of Southbury.
CTDOT bridge identifiers: 07054.

Agency project reference
0130-0191

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Design progress
25% recorded design completion

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Structures / facilities
07054

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Additional scope
Rehabilitation of Bridge No. 07054 (culvert) conveying Eight Mile Brook under Interstate 84 (I-84) in the Town of Southbury.

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Project type
Capital infrastructure project
Recorded constraints and uncertainties
No open solicitation or bid deadline is verified for this record. Confirm procurement requirements with the relevant agency before pursuing a contract.

Contacts

Susan L Morneault

Project lead engineer · Connecticut Department of Transportation

Public project-information contact identified by the agency. Use the designated bidding channel once a solicitation is issued.

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.

Opportunities & Contracts

Planned / Forecast

This agency project record does not establish a currently open solicitation, a bid deadline or a specific unawarded contract package.

Additional scope-based business-development research is available with authorized Infraday+ access.

Companies Involved

Recorded organizations
Connecticut Department of Transportation (managing agency)

Specific roles and award relationships remain subject to source verification.

Budget & Funding

MeaningAmountBasis
Total project estimateUSD 8,382,500CTDOT inventory dated 2026-11-04

Projected · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Construction estimateUSD 7,350,000CTDOT inventory dated 2026-11-04

Projected · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Recorded preliminary engineering expenditureUSD 289,883CTDOT inventory dated 2026-11-04

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.

Timeline & Milestones

Documents & Resources

Updates & Intelligence

Verified research changes

CTDOT project detail

CTDOT figures as of 2026-11-19: construction estimate $7,350,000, preliminary engineering expenditures $292,268. 2026-11-19 | CTDOT reported design 25% complete. CTDOT bridge identifiers: 07054.

Change source ↗

Official-source research expanded

Added source-attributed project details. This enrichment is a research event, not a newly announced project, solicitation or award.

Change source ↗
Earlier recorded updates

2026-11-15: Added from official agency inventory. CTDOT lists the schedule phase as 02 Pre-Design. Source snapshot: 2026-11-04. Project estimates and schedules can change.
2026-11-20 | CTDOT figures as of 2026-11-19: construction estimate $7,350,000, preliminary engineering expenditures $292,268. 2026-11-19 | CTDOT reported design 25% complete. CTDOT bridge identifiers: 07054.