Safety Imprv at Sturtevant St — Norwich (CTDOT 0103-0278)

Norwich, Connecticut · Transportation

Stage: Construction (Pending)Procurement: No procurement verified

Material research update: 2026-11-20 · Source research checked: 2026-11-20

Saved projects appear in your existing research workspace. Saving does not change email preferences.

Total project estimateUSD 10,441,279
Construction estimateUSD 8,458,779
Expected advertisement2026-07-15Forecast only; not an open bid
Construction startNot verified
Project owner
Connecticut Department of Transportation (managing agency)
Delivery method
Not verified
Expected completion
Not verified

Overview

Replace substandard three-cable guiderail with a MASH compliant rail system and improve highway geometry on SR 642 at Sturtevant Street in Norwich (between mile points 1.74 - 1.97). FA# 1103(115)

Agency project reference
0103-0278

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Design progress
100% recorded design completion

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Additional scope
Replace substandard three-cable guiderail with a MASH compliant rail system and improve highway geometry on SR 642 at Sturtevant Street in Norwich (between mile points 1.74 - 1.97). FA# 1103(115)

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Project type
Capital infrastructure project
Recorded constraints and uncertainties
No open solicitation or bid deadline is verified for this record. Confirm procurement requirements with the relevant agency before pursuing a contract.

Contacts

Kevin Blasi

Project manager · Connecticut Department of Transportation

Public project-information contact identified by the agency. Use the designated bidding channel once a solicitation is issued.

Kevin.Blasi@ct.gov

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Mikhail Thomas

Project lead engineer · Connecticut Department of Transportation

Public project-information contact identified by the agency. Use the designated bidding channel once a solicitation is issued.

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.

Opportunities & Contracts

No procurement verified

This agency project record does not establish a currently open solicitation, a bid deadline or a specific unawarded contract package.

Additional scope-based business-development research is available with authorized Infraday+ access.

Companies Involved

CJ Fucci Construction

Contractor listed by CTDOT

Agency-listed relationship; award date, amount and contract package not independently verified

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Budget & Funding

MeaningAmountBasis
Total project estimateUSD 10,441,279CTDOT inventory dated 2026-11-04

Projected · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Construction estimateUSD 8,458,779CTDOT inventory dated 2026-11-04

Projected · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Recorded preliminary engineering expenditureUSD 1,497,902CTDOT inventory dated 2026-11-04

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Recorded right-of-way expenditureUSD 188,582CTDOT inventory dated 2026-11-04

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Recorded construction expenditureUSD 28,717CTDOT inventory dated 2026-11-04

Verified · Connecticut Department of Transportation ↗ · Source 2026-11-04 · Checked 2026-11-15

Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.

Timeline & Milestones

Documents & Resources

Updates & Intelligence

Verified research changes

CTDOT project detail

CTDOT figures as of 2026-11-19: construction estimate $8,458,779, preliminary engineering expenditures $1,497,902, right-of-way expenditures $188,894, construction expenditures $38,038. 2026-11-19 | CTDOT reported design 100% complete.

Change source ↗

Official-source research expanded

Added source-attributed project details. This enrichment is a research event, not a newly announced project, solicitation or award.

Change source ↗
Earlier recorded updates

2026-11-15: Added from official agency inventory. CTDOT lists the schedule phase as 05 Construction (Pending). Source snapshot: 2026-11-04. Project estimates and schedules can change. The source labels construction as pending; work underway is not verified.
2026-11-20 | CTDOT figures as of 2026-11-19: construction estimate $8,458,779, preliminary engineering expenditures $1,497,902, right-of-way expenditures $188,894, construction expenditures $38,038. 2026-11-19 | CTDOT reported design 100% complete.