Port MacKenzie Rail Extension
Alaska · Rail and transit, Transportation
Source research checked: 2026-11-24
Saved projects appear in your existing research workspace. Saving does not change email preferences.
- Project owner
- Alaska Railroad Corporation
- Delivery method
- Not verified
- Expected completion
- Not verified
Overview
The proposed project was selected for Project Development, Final Design, Right-of-Way Acquisition, and Construction and includes the construction of a new 32-mile rail line to connect Port MacKenzie south of Houston, Alaska, to Alaska Railroad’s mainline. The project will create a new port connection to support Alaska’s mineral and energy endowment.
- Project type
- Rail infrastructure
Contacts
Project contact research is not yet verified. Use the official agency contact route while research is completed.
Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.
Opportunities & Contracts
No procurement verified
No linked, currently verified solicitation has been established for this project.
Companies Involved
- Recorded organizations
- Alaska Railroad Corporation
- Recorded providers
- Federal Railroad Administration (CRISI grant to Alaska Railroad Corporation); Alaska Industrial Development and Export Authority (nonfederal matching funds).
Specific roles and award relationships remain subject to source verification.
Budget & Funding
- Recorded funding
- The Alaska Railroad’s $311,315,499 completion plan includes a $249,052,399 federal CRISI award and $62,263,100 in nonfederal match. The railroad budgets $32,671,964 in cash from AIDEA. AIDEA announced a matching commitment of up to $34 million on October 20. Its June 17 resolution lets the executive director use the revolving fund for the match and other Port MacKenzie project costs within that ceiling.
Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.
Timeline & Milestones
- Recorded milestones
- 2026-10-19: Federal funding selection announced.
2026-11-24: AIDEA board recessed without acting on G26-07. Scheduled resumption: November 27 at 10 a.m. Alaska time.
Documents & Resources
- FY2025–2026 FRA CRISI official project list ↗Port MacKenzie Rail ExtensionReviewed 2026-10-29
- Alaska Industrial Development and Export Authority, signed June funding resolution ↗2026-06-17Reviewed 2026-11-24
- AIDEA, October 20 announcement of matching funds for the Port MacKenzie Rail Extension ↗2026-10-20Reviewed 2026-11-24
- Alaska Railroad, November 17 board packet, Resolution 2026-26 and expenditure plan 11515 (pp. 122–130) ↗2026-11-17Reviewed 2026-11-24
- AIDEA board meeting schedule ↗2026-11-24Reviewed 2026-11-24
- Infraday reporting on the Port MacKenzie Rail Extension ↗Related reportingUpdated 2026-11-24
Updates & Intelligence
Earlier recorded updates
2026-11-24: Robyn L. Reyes, AIDEA’s engagement and communications specialist, wrote to Infraday on November 24, “The Board did not take any action on the Amended Second Resolution G26-07 in today's Board meeting as it is currently in recess and will resume at 10:00 AM on Friday, November 27, 2026.” AIDEA did not specify an amount under an executed agreement, disbursements to date or the conditions for the next payment.
2026-10-29: Source reviewed. The cited federal award list verifies funding selection and the proposed scope. Selection for design or construction funding does not establish that work has started. Current construction progress, open procurement, contractor appointments and completion dates have not been independently confirmed.
Detailed research and a source-backed change history are being assembled. A routine source check is not a material project update.