- Project owner
- City of Acworth
- Delivery method
- Not verified
- Expected completion
- Not verified
Overview
USDOT selected City of Acworth for a $13,711,200 FY 2026 SS4A implementation grant. The project will implement corridor safety improvements on Nance Road, Acworth Summit Boulevard, and Acworth Due West Road.
Technical scope
The project will implement corridor safety improvements on Nance Road, Acworth Summit Boulevard, and Acworth Due West Road. The project will install single-lane roundabouts at high-crash intersections, add dedicated turn lanes, improve access management, close sidewalk gaps, upgrade curb ramps and crosswalks, modernize traffic signals, and complete drainage and pavement improvements. Between 2020 and 2024, the corridor recorded 535 crashes, including 1 fatal crash and multiple serious injuries, with rear-end and angle crashes driving the safety need. The improvements target locations on the high-injury network and apply FHWA Proven Safety Countermeasures to reduce conflict points, lower crash severity, and improve conditions for motorists and pedestrians. The project is identified in the Cobb County Comprehensive Safety Action Plan and is expected to improve intersection operations and emergency response reliability along this east-west corridor.
- Project type
- Road safety infrastructure
Contacts
Project contact research is not yet verified. Use the official agency contact route while research is completed.
Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.
Opportunities & Contracts
No procurement verified
No linked, currently verified solicitation has been established for this project.
Companies Involved
- Recorded organizations
- Lead applicant: City of Acworth; federal grant program: U.S. Department of Transportation, Safe Streets and Roads for All.
Specific roles and award relationships remain subject to source verification.
Budget & Funding
- Reported project value
- $17,139,001 total project cost in the FY 2026 award record; award-time scope and estimate.
- Recorded funding
- $13,711,200 FY 2026 SS4A implementation grant selected by USDOT on October 30, 2026. Grant selection is not proof of obligation, disbursement or a construction contract award.
Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.
Timeline & Milestones
- Recorded milestones
- 2026-10-30: FY 2026 SS4A award announced.
Documents & Resources
- USDOT FY 2026 SS4A full award list ↗2026-10-30Applicant, project scope, state, grant type, federal award and total project cost
- USDOT FY26 SS4A award workbook ↗2026-10-30Project: Nance Rd Corridor Safety Improvements Project; applicant: City of Acworth
Updates & Intelligence
Earlier recorded updates
2026-11-08: Added verified applicant, award scope, total project cost, selected federal grant and state from the October 30, 2026 USDOT workbook. Award announced October 30, 2026. This record describes the selected grant scope. Construction progress, contract awards, delivery dates and open procurement have not been established by the award workbook.
Detailed research and a source-backed change history are being assembled. A routine source check is not a material project update.