Justified Data Campus
Hawesville, Kentucky · Data centers
Source research checked: Not recorded
Saved projects appear in your existing research workspace. Saving does not change email preferences.
- Project owner
- TeraWulf
- Delivery method
- Guaranteed-maximum-price EPC agreement
- Expected completion
- Phased ready-for-service: late 2027 through second quarter 2028
Overview
Three-building data center campus serving Anthropic under long-term contracted leases.
Technical scope
Engineering, procurement, construction, testing and commissioning for three data center buildings.
- Project type
- AI / high-performance computing data center campus
- Recorded constraints and uncertainties
- Debt amount and final EPC pricing remain undisclosed; delivery depends on financing and execution milestones.
Contacts
Project contact research is not yet verified. Use the official agency contact route while research is completed.
Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.
Opportunities & Contracts
No procurement verified
No linked, currently verified solicitation has been established for this project.
Previously recorded contract activity
No open procurement established; Fluor EPC agreement is definitive
Recorded activity is not confirmation that a solicitation remains open.
Previously recorded anticipated work
Not announced
- Recorded package values
- EPC price undisclosed; GMP being established
Companies Involved
- Recorded organizations
- TeraWulf; Anthropic; Google; Fluor Enterprises
- Recorded design firm
- Fluor under EPC scope
- Recorded contractor
- Fluor Enterprises, Inc.
Specific roles and award relationships remain subject to source verification.
Budget & Funding
- Reported project value
- Project cost undisclosed; approximately $19 billion represents contracted lease commitments, not project cost or financing
- Recorded funding
- Google contractual credit support for anticipated debt financing; debt amount undisclosed
Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.
Timeline & Milestones
- Recorded construction start
- Early works under way as of November 4, 2026
- Recorded completion
- Phased ready-for-service: late 2027 through second quarter 2028
- Recorded milestones
- 2026-03-16: Fluor limited notice to proceed announced.
2026-11-04: Definitive Fluor EPC and Google credit-support agreements announced.
Late 2027–Q2 2028: phased ready-for-service targets.
Documents & Resources
- TeraWulf announcement ↗2026-11-04owner, tenant, financing support, EPC role, schedule
- TeraWulf 8-K ↗2026-11-04lease capacity, credit support and milestone terms
Updates & Intelligence
Earlier recorded updates
Development date: 2026-11-04
What changed: TeraWulf executed Google credit-support agreements and a definitive Fluor EPC agreement.
Why it matters: Financing support and awarded EPC capacity move three buildings toward phased delivery.
History:
2026-11-05: New Infraday Projects record added.
Detailed research and a source-backed change history are being assembled. A routine source check is not a material project update.