I-5 – 0.1 Miles N. of Koontz Rd to SR 507 – Paver
Lewis County, Washington · Transportation, Highways and bridges
Source research checked: 2026-11-06
Saved projects appear in your existing research workspace. Saving does not change email preferences.
- Project owner
- Washington State Department of Transportation
- Delivery method
- Not verified
- Expected completion
- Fall 2026: Construction scheduled for completion.
Overview
Rehabilitate an 11-mile section of I-5 in Lewis County through resurfacing, drainage and pavement repairs, followed by deck and joint work on five bridges.
Technical scope
Rehabilitate an 11-mile section of I-5 in Lewis County through resurfacing, drainage and pavement repairs, followed by deck and joint work on five bridges.
Agency-published project contact: Kelso Area Engineering Office | (360) 905-1599 | swkelso@wsdot.wa.gov
Contact source: https://wsdot.wa.gov/construction-planning/search-projects/i-5-01-miles-n-koontz-rd-sr-507-paver
- Project type
- Road, bridge and multimodal improvements
Contacts
Recorded professional contact
Kelso Area Engineering Office | (360) 905-1599 | swkelso@wsdot.wa.gov
Recorded contact information. Current role and contact reachability have not been independently rechecked; confirm through the linked source before outreach.
Recorded contact source ↗Source check recorded: 2026-11-06
Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.
Opportunities & Contracts
No procurement verified
No linked, currently verified solicitation has been established for this project.
Companies Involved
- Recorded contractor
- Granite Construction Company (agency-reported award: June 25, 2025)
Specific roles and award relationships remain subject to source verification.
Budget & Funding
- Reported project value
- $9.164 million estimated project cost
- Recorded funding
- Agency funding detail (2026-11-06): The cost of this project is approximately $9.164 million dollars and is made up for state and federal funding.
Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.
Timeline & Milestones
- Recorded construction start
- Aug. 2025: Construction started
- Recorded completion
- Fall 2026: Construction scheduled for completion.
- Recorded milestones
- Agency-listed project timeline: Spring 2025 - Fall 2026. Agency stage: Construction.
Agency milestone schedule (reviewed 2026-11-06):
Spring 2025: Project went to competitive bidding
June 25, 2025: Project awarded to Granite Construction Company
Aug. 2025: Construction started
Fall 2026: Construction scheduled for completion.
Documents & Resources
- WSDOT official project page ↗Reviewed 2026-11-06
Updates & Intelligence
Earlier recorded updates
2026-11-06: Newly indexed from the agency project page. Agency-listed project timeline: Spring 2025 - Fall 2026. Agency stage: Construction. Procurement availability has not been verified.
2026-11-06: Official-source enrichment added or expanded contacts, milestones, funding, start, completion, contractor, scope. Planned procurement milestones do not establish an open bid.
Detailed research and a source-backed change history are being assembled. A routine source check is not a material project update.