Hill Air Force Base East Campus
Hill Air Force Base, Utah · Defense infrastructure
Source research checked: 2026-11-12
Saved projects appear in your existing research workspace. Saving does not change email preferences.
- Project owner
- U.S. Air Force
- Delivery method
- Not verified
- Expected completion
- Infrastructure completion goal 2032; site preparation targeted September 2028
Overview
Six-facility aircraft maintenance and training campus supporting F-35 Lightning II fighters and T-7A Red Hawk training aircraft.
Technical scope
Deliver airfield paving and lighting, water, electrical, fire suppression, sewer, communications, roads and sidewalks for six planned facilities, including F-35 repair/training and maintenance facilities and a T-7A depot hangar.
- Project type
- Military aircraft maintenance campus
- Recorded constraints and uncertainties
- Exact solicitation timing, requirements and eligibility for the planned fiscal-2027 progressive design-build acquisition have not been announced.
Contacts
Project contact research is not yet verified. Use the official agency contact route while research is completed.
Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.
Opportunities & Contracts
No procurement verified
No linked, currently verified solicitation has been established for this project.
Companies Involved
- Recorded organizations
- U.S. Air Force; USACE Sacramento District
- Recorded contractor
- One infrastructure contractor selected; name not disclosed in source
Specific roles and award relationships remain subject to source verification.
Budget & Funding
- Reported project value
- USD 1.2 billion — planned Air Force investment over five years
Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.
Timeline & Milestones
- Recorded construction start
- Groundbreaking held spring 2026; utility construction active by November 2026
- Recorded completion
- Infrastructure completion goal 2032; site preparation targeted September 2028
- Recorded milestones
- 2026-11-10 — Fire-suppression, sewer and communications systems reported substantially complete.
2028-09 — Site preparation targeted for completion.
FY2027 — USACE plans to seek proposals and award a combined progressive design-build project for two F-35 facilities.
2032 — Infrastructure completion goal.
Documents & Resources
- Official project source ↗Reviewed 2026-11-12owner, location, value basis, stage, scope and milestones
- Related Infraday News ↗2026-11-12
Updates & Intelligence
Earlier recorded updates
2026-11-12: Added from USACE November 10 update. The planned fiscal-2027 acquisition is not a current open solicitation.
Detailed research and a source-backed change history are being assembled. A routine source check is not a material project update.