Fairfax County Parkway widening north
Fairfax County, Virginia · Transportation, Highways and bridges
Source research checked: 2026-11-06
Saved projects appear in your existing research workspace. Saving does not change email preferences.
- Project owner
- Virginia Department of Transportation
- Delivery method
- Not verified
- Expected completion
- Mid-2027
Overview
Widen approximately four miles of northern Fairfax County Parkway to six lanes, including bridge widening, noise barriers and an acceleration lane.
Technical scope
Widen approximately four miles of northern Fairfax County Parkway to six lanes, including bridge widening, noise barriers and an acceleration lane.
Agency project references: UPC: 107937; State ID: 0286-029-259, B628, B630, B631, B632, C501, D605, P101, R201; Federal ID: STP-5A01 (775), STP-5B01 (309).
Agency-published project contact: Shawn Faull | Construction | shawn.faull@vdot.virginia.gov | 571-419-1642
Contact source: https://www.vdot.virginia.gov/projects/northern-virginia-district/fairfax-county-parkway-widening-north/
- Project type
- Road, bridge and multimodal improvements
Contacts
Recorded professional contact
Shawn Faull | Construction | shawn.faull@vdot.virginia.gov | 571-419-1642
Recorded contact information. Current role and contact reachability have not been independently rechecked; confirm through the linked source before outreach.
Recorded contact source ↗Source check recorded: 2026-11-06
Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.
Opportunities & Contracts
No procurement verified
No linked, currently verified solicitation has been established for this project.
Companies Involved
Specific roles and award relationships remain subject to source verification.
Budget & Funding
- Reported project value
- $109.4 million (agency estimate)
Agency cost detail (2026-11-06): Preliminary engineering: $16.8 million; Right of way acquisition and utility relocation: $2.2 million; Construction: $90.4 million. Components are not separate contract awards.
Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.
Timeline & Milestones
- Recorded construction start
- June 2024
- Recorded completion
- Mid-2027
- Recorded milestones
- Agency status: Under construction. Agency schedule entry: June 2024. Estimated completion: Mid-2027.
Documents & Resources
- Virginia Department of Transportation official project page ↗Reviewed 2026-11-06
Updates & Intelligence
Earlier recorded updates
2026-11-06: Newly indexed from the agency project page. Agency status: Under construction. Agency schedule entry: June 2024. Estimated completion: Mid-2027. Procurement availability has not been verified.
2026-11-06: Official-source enrichment added or expanded contacts, latitude, longitude, scope, value. Planned procurement milestones do not establish an open bid.
Detailed research and a source-backed change history are being assembled. A routine source check is not a material project update.