Colorado’s Power Pathway

Eastern Colorado

Estimated value$1.7B
StageUnder construction
Owner / developerXcel Energy / Public Service Company of Colorado
Last verified2026-09-30

Project overview

Approximately 550 miles of double-circuit transmission and new or expanded substations. The owner reports Segments 1, 2 and 3 in service, with construction continuing on Segment 4 and portions of Segment 5.

Scope
Approximately 550 miles of double-circuit transmission and new or expanded substations. The owner reports Segments 1, 2 and 3 in service, with construction continuing on Segment 4 and portions of Segment 5.
Project type
345 kV transmission system
Reported investment / scope
Approximately $1.695 billion forecast in April 2026 report
Funding sources
Not available
Delivery method
Not available

Organizations involved

Owner / developer
Xcel Energy / Public Service Company of Colorado
Developer
Not available
Engineering firm / architect
Not available
General contractor / construction manager
Not available
EPC contractor
Not available
Technology / equipment providers
Not available
Financial sponsor
Not available
Other recorded participants
Not available

Business opportunities

Not verified

Current procurement record
Not available
Upcoming procurement
Not available
Contract / package value
Not available
Supplier / subcontractor opportunities
Not available
Workforce requirements
Not available

Check official project / procurement portal ↗

A project listing is not an open solicitation. Check the source for eligibility, current status, closing time and addenda.

Timeline & key dates

Expected procurement
Not available
Construction start
Not available
Estimated completion
Remaining segments targeted for 2027; schedules vary by segment
Dated milestones
Not available
Permitting
Not available
Recent project updates
Added September 30, 2026 following review of the linked source. Announced schedules are labeled as targets; map pin is approximate.
Challenges / risks
Not available

Related intelligence

No verified record associations have been entered for this project yet.

Connections use recorded entity IDs and public evidence. Shared keywords do not establish a relationship.

Additional project record

Approximately 550 miles of double-circuit transmission and new or expanded substations. The owner reports Segments 1, 2 and 3 in service, with construction continuing on Segment 4 and portions of Segment 5.

Owner: Xcel Energy / Public Service Company of Colorado. Stage: Construction. Reported investment: Approximately $1.695 billion forecast in April 2026 report. Schedule: Remaining segments targeted for 2027; schedules vary by segment.

Official project source. Source reviewed September 30, 2026.

Saved searches & recent searches

Sign in to keep searches across devices. Your recent searches on this device appear below.

Join Infraday Free · Sign in
You’re offline. Reconnect to load the latest Infraday updates.