Chickamauga Lock Replacement
Chattanooga, Tennessee · Ports and maritime, Transportation
Material research update: 2026-11-27 · Source research checked: 2026-11-27
Saved projects appear in your existing research workspace. Saving does not change email preferences.
- Project owner
- U.S. Army Corps of Engineers, Nashville District
- Delivery method
- Upstream approach completed, final contract awarded
- Expected completion
- Not verified
Overview
Replacement navigation lock and approach walls on the Tennessee River; USACE terminated the chamber contract in May 2026 while other packages continue.
- Additional scope
- At Chickamauga Dam in Chattanooga, Tennessee, the Army Corps of Engineers has finished a structure that tug and tow pilots will use to line up for a much larger lock. The Nashville District marked completion of the upstream approach wall on November 16. Commercial traffic will move to the new lock during a separate contract that the Corps awarded in February.
Verified · Nashville District approach wall completion ↗ · Source 2026-11-16 · Checked 2026-11-27
- Project type
- Inland navigation lock replacement
Contacts
Project contact research is not yet verified. Use the official agency contact route while research is completed.
Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.
Opportunities & Contracts
No procurement verified
No linked, currently verified solicitation has been established for this project.
Companies Involved
U.S. Army Corps of Engineers ↗
Nashville District manages the lock contracts.
Nashville District manages the lock contracts.
Verified · Nashville District approach wall completion ↗ · Source 2026-11-16 · Checked 2026-11-27
C.J. Mahan Construction Company ↗
Built the upstream guide wall and holds the final lock contract.
Built the upstream guide wall and holds the final lock contract.
Verified · Nashville District approach wall completion ↗ · Source 2026-11-16 · Checked 2026-11-27
Budget & Funding
Project cost and funding have not yet been verified.
Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.
Timeline & Milestones
Project-specific schedule milestones have not yet been verified.
Documents & Resources
Source document
Verified · Nashville District approach wall completion ↗ · Source 2026-11-16 · Checked 2026-11-27
Source document
Verified · Final approach and decommissioning contract award ↗ · Checked 2026-11-27
Infraday news coverage
Verified · Infraday ↗ · Source 2026-11-28 · Checked 2026-11-28
Updates & Intelligence
Earlier recorded updates
Source review: 2026-10-03
Replacement navigation lock and approach walls on the Tennessee River; USACE terminated the chamber contract in May 2026 while other packages continue.
November 2026 | The contractor that built the guide wall also holds the final contract to connect the new Tennessee River lock and bring it into service. | https://www.dvidshub.net/news/579490/ribbon-cutting-marks-completion-chickamauga-lock-upstream-approach-wall-contract