Bus stop and pedestrian improvements, Augusta County and City of Waynesboro
Augusta County, Waynesboro, Virginia · Transportation
Source research checked: 2026-11-06
Saved projects appear in your existing research workspace. Saving does not change email preferences.
- Project owner
- Virginia Department of Transportation
- Delivery method
- Not verified
- Expected completion
- Summer 2027
Overview
Improve BRITE transit access at three Augusta County and Waynesboro locations through bus shelters, pull-offs, accessible sidewalks and pedestrian crossings.
Technical scope
Improve BRITE transit access at three Augusta County and Waynesboro locations through bus shelters, pull-offs, accessible sidewalks and pedestrian crossings.
Agency project references: UPC: 119655; State ID: 0250-007-031, C501, P101, R201; Federal ID: NHPP-007-8(164).
Agency-published project contact: Keith N. Harrop, P.E. | Area Construction Engineer | keith.harrop@VDOT.Virginia.gov | (434) 962-2285
Contact source: https://www.vdot.virginia.gov/projects/staunton-district/augusta-county-and-waynesboro---bus-stop-and-pedestrian-improvements/
- Project type
- Pedestrian, cycling and transit access improvements
Contacts
Recorded professional contact
Keith N. Harrop, P.E. | Area Construction Engineer | keith.harrop@VDOT.Virginia.gov | (434) 962-2285
Recorded contact information. Current role and contact reachability have not been independently rechecked; confirm through the linked source before outreach.
Recorded contact source ↗Source check recorded: 2026-11-06
Use the issuing agency’s designated bidding channel for solicitation questions. Project contacts are not a route around procurement restrictions.
Opportunities & Contracts
No procurement verified
No linked, currently verified solicitation has been established for this project.
Companies Involved
Specific roles and award relationships remain subject to source verification.
Budget & Funding
- Reported project value
- $3.3 million (agency estimate)
Agency cost detail (2026-11-06): Preliminary engineering: $708,818; Right of way/utility relocation: $345,346; Construction: $2,199,150; Total: $3,253,314; In July 2026, VDOT awarded a construction contract for $2,110,496.53 to Richardson-Wayland-Ferreira, LLC of Roanoke, Va.. Components are not separate contract awards.
Project estimates, construction estimates, programmed funding and expenditure are separate figures. None establishes an available contract package.
Timeline & Milestones
- Recorded completion
- Summer 2027
- Recorded milestones
- Agency status: Under construction. Agency schedule entry: Spring 2026 (advertise for construction). Estimated completion: Summer 2027.
Documents & Resources
- Virginia Department of Transportation official project page ↗Reviewed 2026-11-06
Updates & Intelligence
Earlier recorded updates
2026-11-06: Newly indexed from the agency project page. Agency status: Under construction. Agency schedule entry: Spring 2026 (advertise for construction). Estimated completion: Summer 2027. Procurement availability has not been verified.
2026-11-06: Official-source enrichment added or expanded contacts, scope, value. Planned procurement milestones do not establish an open bid.
Detailed research and a source-backed change history are being assembled. A routine source check is not a material project update.