Capital & Policy · Otero County, New Mexico
Greenvolt starts New Mexico solar and storage project backed by $190 million in financing
Two construction teams will deliver the generating plant and its grid connection in Otero County. Tri-State has agreed to buy the output.

Greenvolt Power has begun construction of the Alamogordo solar and battery project in Otero County, New Mexico, with a long-term buyer for its output and financing arranged with MUFG Bank and ING Capital. The developer expects to finish the project in summer 2028. Its November 25 announcement identifies who will build both sides of the connection between the generating plant and the transmission system.
The solar plant is rated at 100 megawatts of alternating-current output. Alongside it, Greenvolt plans a battery capable of delivering 50 megawatts and storing 200 megawatt-hours. At its rated output, that works out to four hours of discharge. For Tri-State Generation and Transmission, the buyer under the power purchase agreement, storage adds the ability to take power at a different time from when the panels generate it.
Greenvolt divided delivery between two engineering and construction contractors. CJR Renewables will build the solar installation and the battery facility. Dashiell Corporation will build the substation and switchyard. Greenvolt says the transmission owner will take over the latter facilities once the project enters commercial operation. That handoff gives grid connection work a distinct place in the construction schedule.
The $190 million financing package comprises a construction-to-term loan, a bridge loan and a letter of credit facility. Those instruments serve different purposes, so their combined face value cannot be read as the construction price. Greenvolt did not disclose a price for the power purchase agreement or individual contract values for the two builders. The next milestone for the buyer is the move from construction to an operating plant that can deliver power to the system.
Key details
- Project scale
- $190 million financing package
Watch for the grid handover and targeted summer 2028 completion.
Review the official next step →Infraday Intelligence
Greenvolt Power
Project developer and construction sponsor.
Tri-State Generation and Transmission Association
Long-term power buyer for the Alamogordo project.
CJR Renewables
Builds the solar and battery facilities.
Dashiell Corporation
Builds the substation and switchyard.
MUFG
MUFG Bank helped structure the $190 million financing.
ING Capital LLC
ING Capital LLC helped structure the $190 million financing.
Related research
Primary sources
- Greenvolt construction and financing announcement
- Independent project coverage
- Greenvolt Power contractor roles and financing terms
Have a correction or information about this story? Contact Infraday.
THE INFRADAY WIRE
Your weekly infrastructure briefing.
The projects, investment, companies and developments moving the infrastructure economy, delivered to your inbox.
Projects. Capital. Policy. Markets.
Free weekly newsletter. Unsubscribe anytime.
The form is taking longer to load. Refresh the page or contact Infraday.