Data Centers & Digital Infrastructure · Texas

Most large computing loads fell short in Texas grid simulations

Only 31% of the large computing loads ERCOT tested met its voltage ride-through requirement in simulations. Developers get one window to revise their models.

Infraday News Desk · Based on official sourcesPublished
Rows of server cabinets flank an aisle inside Oracle’s Abilene data center.
Inside a data hall at Oracle’s Abilene, Texas, campus on September 17, 2025. Robert Harbison / Oracle · Photo source

The Electric Reliability Council of Texas reported on November 19 that only 31% of the large computing loads it tested could ride through a simulated voltage disturbance. ERCOT ran models for roughly 260 large-load projects as part of its first group study for grid connections. For AI developers promising customers a date when servers will be ready, the results identify a question a signed contract cannot settle on its own. Can the facility draw power in the way the grid operator requires?

Grid planners use a computer model to see how a facility would respond if voltage dropped briefly on the transmission system. A campus that switches to backup power might keep its servers running while abruptly removing much of its demand from the grid. ERCOT identified two common problems. Some models showed all or part of the load dropping away. Others showed demand returning too slowly. The tests measured how the submitted designs performed in simulation. ERCOT did not report outages at operating campuses.

What the 410 GW figure measures

In March, ERCOT tracked about 410 gigawatts of large loads seeking connections through 2030. Data centers accounted for nearly 88% of that capacity. The most telling figure was one row down in the grid operator’s breakdown. About 294 GW fell into the category for projects that had yet to submit planning studies. ERCOT had observed about 5.8 GW energized. Treating the whole queue as a forecast would count projects at those two very different stages on the same terms.

In June, Texas utility regulators approved a process known as Batch Zero for qualifying projects seeking at least 75 megawatts. Studying several large customers together lets ERCOT see how much electricity a location can serve if multiple campuses arrive on similar schedules. It also helps identify where transmission upgrades will be needed. For a developer evaluating a site, both the available capacity and the timing of those upgrades matter.

Communities have a different question. How much water and power should they plan for when some developers are still choosing their equipment? In a separate ERCOT survey, 433 respondents represented about 177 GW of requested connections. West Texas accounted for about 73 GW, the largest share of any load zone. Cooling was the subject on which developers most often lacked a definitive answer. The survey covered a different group from the March queue and the November engineering tests.

Two Texas campuses, two ways to supply power

Oracle’s Abilene campus already runs AI workloads. It draws electricity directly from the Texas grid and uses natural gas turbines for backup. At its next campus in Shackelford County, Oracle plans to rely on an on-site power system built with reciprocating engines. On November 20 the company said the second site had its permits and that it expected to hand over NVIDIA Vera Rubin server racks in the coming weeks. It also said it had secured the funding it needed for its OpenAI contract.

In a market commentary for Seeking Alpha, Jennifer Warren identified reliable power and customers’ ability to honor long-term contracts as constraints on AI construction. For a customer buying computing capacity, the milestones in Oracle’s announcement answer different questions. Financing pays for construction and equipment. A permit allows a specified activity. Handing over server racks gives a customer a delivery milestone it can check. The two campuses also illustrate why a gigawatt of proposed computing capacity does not always translate into a gigawatt of new demand on the public grid.

Environmental reviews are moving again. The Texas Commission on Environmental Quality told The Texas Tribune on November 17 that it had resumed its normal permit reviews after the governor’s office notified it that ERCOT had gathered community-impact information. Governor Greg Abbott had ordered a pause in September. Individual applications still go through the agency’s review. ERCOT is targeting December 10 for its final community-impact report.

Developers in Batch Zero face a nearer engineering decision. ERCOT plans to send individual test results in early December and give applicants one opportunity to submit updated models. For projects subject to the ride-through rule, a model that meets the requirement is necessary to enter the quarterly stability assessment. ERCOT requires that assessment before it will authorize a project to draw power for the first time.

Oracle Construction and Engineering is a sponsor of Infraday East 2026.

Have a correction or information about this story? Contact Infraday.

ERCOT expects to send developers their individual simulation results in early December 2026.

Review the official next step →

Infraday+ research

Stargate Abilene AI Data Center Campus

Oracle’s Abilene campus draws electricity from the Texas grid · Project Intelligence

Primary sources

Additional reporting