SFO readies pumps as Caltrans closes Posey Tube ahead of king tides

SFO has budgeted $130 million for shoreline review, mitigation and permits. Across the bay, Oakland has already raised a 4.5-mile dike to protect its airfield.

Infraday News Desk · Based on official sourcesPublished
An aircraft wing above SFO’s rock-lined shoreline, with the airfield to the left and San Francisco Bay to the right.
The shoreline at San Francisco International Airport, seen from a landing flight on January 28, 2026. 4300streetcar / Wikimedia Commons, CC BY 4.0. Resized. · Photo source

San Francisco International Airport had pumps ready on Sunday, November 22, as the Bay Area prepared for exceptionally high tides during Thanksgiving week. Across the bay, Caltrans closed the Posey Tube from Alameda to Oakland at 8 p.m. The agency scheduled the tunnel to reopen Friday, subject to water levels and weather.

A National Weather Service coastal flood warning covered the San Francisco and San Pablo bay shorelines through 4 p.m. Pacific on Thanksgiving Day. Its Monday morning forecast put the week’s highest tide at the San Francisco gauge on Wednesday at 10:49 a.m., about 2.7 feet above normal. That prediction is for the gauge. Water levels and the timing of high tide vary around the bay.

What SFO can do during a high tide

Airport Director Mike Nakornkhet outlined the preparations at the November 3 Airport Commission meeting. The National Weather Service had briefed the airport, crews had inspected the site, and the facilities team had made arrangements for extra pumping and backup power. An airport official confirmed to CBS News Bay Area on Sunday that pumps were ready. SFO advised passengers to check flight status with their airline.

Pumping is part of the airport’s everyday flood protection. When bay water comes over a shoreline barrier, SFO’s storm drains collect it and pumps move it back into the bay. The holiday rush raises the stakes for keeping the runways available. A week before the flood warning, SFO forecast 6.7 million travelers between Thanksgiving and New Year’s Day, up 8% from the previous holiday season.

Two airports, different stages of shoreline work

SFO has about eight miles of shoreline. Berms, seawalls and sheet piling protect more than six of them. Its long-term Shoreline Protection Program aims to keep the airfield and other airport facilities protected through about 2085. The design allows for 42 inches of sea-level rise together with a storm that has a 1% chance of occurring in any given year.

In its June 8 bond disclosure, the airport identified $130 million in its capital plan for environmental review, mitigation, permits and coordination with neighboring cities and agencies. A 2019 feasibility study put the program at $587 million in 2018 dollars. SFO now expects it to cost significantly more. On November 3, commissioners approved two more years of engineering support from COWI-TERRA Joint Venture and raised the ceiling on that existing contract by $900,000 to $6.9 million.

Oakland San Francisco Bay Airport is further along. The Port of Oakland raised its 4.5-mile perimeter dike in a first phase completed in 2022. In June the port said crews were finishing a second phase to strengthen the soil beneath the dike against earthquakes. The port put the two phases at about $80 million, including $32 million in federal airport improvement funds for the seismic work. UC Davis researcher Fraser Shilling cited the levee improvements in an October report as one reason Oakland’s airfield faces less exposure to high water, even as nearby roads remain at risk.

A closure on one side of the crossing

For Alameda, the immediate disruption is directional. The Posey Tube normally carries traffic off the island toward Oakland. The Webster Tube, which carries traffic into Alameda, was scheduled to remain open. Caltrans directed Oakland-bound drivers to the Park Street, Fruitvale Avenue and High Street bridges. The Posey closure also applies to people walking or cycling.

Caltrans said it closed the tube ahead of the tides because flood damage could mean a much longer shutdown for repairs. Its scheduled reopening is 5 p.m. Pacific on Friday, November 27. SFO’s next capital decision is further out. The airport’s June disclosure targeted mid-2027 for federal environmental review, mitigation and permitting. Once that work is complete, the airport says it can determine the full cost and when construction can begin.

Additional reporting by John Ramos, CBS News Bay Area, November 23, 2026.

Have a correction or information about this story? Contact Infraday.

Caltrans scheduled the Posey Tube to reopen at 5 p.m. Pacific on November 27, subject to conditions.

Review the official next step →

Infraday+ research

California Department of Transportation (Caltrans)

California Department of Transportation (Caltrans)

Primary sources

You’re offline. Reconnect to load the latest Infraday updates.