AI Infrastructure · Global | North Yorkshire, United Kingdom

Infrastructure funds raise $62 billion in one quarter as AI developers seek power

A proposed 100-megawatt data center at a Yorkshire power station shows what it takes to turn an investor commitment into a construction contract.

Infraday News Desk · Based on official sourcesPublished
Aerial view of Drax Power Station and its cooling towers near Selby in North Yorkshire.
Drax Power Station near Selby, North Yorkshire, on February 21, 2026. The partners propose building the first data hall on the existing power station estate. Simon Tomson / Geograph, CC BY-SA 2.0 · Photo source

Private infrastructure funds worldwide raised $62 billion from July through September, more than they raised in the first six months of 2026 combined. Preqin counted 21 funds in the third quarter, when several large funds finished raising money. The figures have drawn attention as artificial intelligence companies compete for power and data center space. Preqin’s total covers the entire infrastructure market, including sectors such as energy and transport.

One place to see what those commitments can buy is an existing power station near Selby in northern England. Brookfield and its partners want to build a data center there. They have land, access to the grid and an estimate of the investment required. They are still seeking a tenant for the first phase, and North Yorkshire Council has yet to receive the planning application, according to the project’s public consultation.

What the $62 billion measures

Preqin recorded $101 billion across 65 funds in the first nine months of the year. That puts the first half at approximately $39 billion and gives the third quarter about 61% of the nine-month total. The timing of a few large fund closings can move that percentage considerably. It tells a contractor something about the capital managers can draw on, but little about when a particular owner will order equipment or award work.

Brookfield Asset Management’s November 6 results show how the numbers overlap. Clients had committed about $50 billion to its infrastructure strategies over the preceding year. That figure included $26 billion for its flagship strategy. Of the flagship total, $13 billion came in after September 30. Adding either Brookfield figure to Preqin’s third-quarter tally would mix reporting periods and different stages of fundraising.

Which revenues keep pace with inflation?

In its November investment review, J.P. Morgan Private Bank identified a feature that matters more to an owner than the label on a fund. A multiyear contract can allow an operator to raise the price it charges as costs rise. An investor can read the agreement to see which index applies, how often the price changes and who bears any increase in the meantime. A developer still looking for its first customer has no comparable stream of payments.

Investors also face a longer wait to get their cash back. Boston Consulting Group found that the 50 largest infrastructure fund managers had held their portfolio companies for an average of 7.6 years in 2025, up from 6.1 years in 2021. Some recent sales moved businesses into new funds managed by the same firm. Those transfers can give earlier investors a chance to sell while the manager continues to own and operate the business through another fund.

A 100-megawatt test in North Yorkshire

Under the partnership announced November 3, Drax would provide land and power infrastructure. Brookfield and its UK platform, Radiant, would develop and operate the data center, with backing from Brookfield’s joint venture with Qai. The initial design puts a data hall, cooling systems and electrical plant on previously developed land at the south end of the station. The first phase would draw electricity from the grid.

Brookfield estimated that the first phase could require £2.5 billion for up to 100 megawatts of capacity. Its estimate of more than £20 billion for the full development includes semiconductor chips. For contractors sizing the opportunity, that distinction matters. The larger figure combines buildings and power equipment with the computing hardware that goes inside them, and it assumes the partners proceed with later phases.

Drax’s public consultation closes December 3. The project team says it will review responses before submitting its application to North Yorkshire Council. To reach their target of starting operations in the first quarter of 2028, the partners must also secure a tenant, obtain network and regulatory approvals, agree on commercial terms and each make a final investment decision. Those are the milestones that would move the project from a proposed use of capital to a construction commitment.

Have a correction or information about this story? Contact Infraday.

Drax’s public consultation closes December 3, ahead of a planning application to North Yorkshire Council.

Review the official next step →